31 May 2023 · Delegated - Principal Planner (Abigail Morgan)
17, Royal Park, Ramsey, Isle Of Man, IM8 3uf
This application sought to provide information to satisfy specific conditions from a previous approval (22/00520/B) for a dwelling, covering tree protection along the western boundary (Condition 2), surface water drainage (Condition 3), soft landscaping between the dwelling and highway (Condition 8), and cycle storage …
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer assessed submitted plans against the specific conditions of prior approval 22/00520/B and found them satisfactory.
no objection (23.05.2023) to the tree protection plan; monitoring scheme should be carried out as planned
no objection (19.04.2023) to the surface water drainage plan
no objection (17.03.2023) to the soft landscaping plan besides the species for the hedge at the rear boundary (subsequently amended to a local species)
Consultation responses from Highways/Drainage, DEFA Biodiversity, and DEFA Forestry on discharge of conditions for PA 22/00520/B generally support the submitted details with minor comments.
Key concern: cherry laurel hedging considered invasive
Highway Development Control Officer
No ObjectionAs this was a condition added by the Inspector / Minister, we have no further comment to make to that of Chris Kershaw.; Runoff from the private driveway will not impact on the existing public highway as it falls back toward the property.
DEFA Biodiversity
Conditional No ObjectionApart from the cherry laurel hedging, which I would not recommend as we consider it invasive, though it is not yet listed on Schedule 8 of the Wildlife Act 1990, I think the other gardens details, including the bird box location and type are satisfactory.
Conditions requested: avoid cherry laurel hedging
DEFA Forestry
No ObjectionI can confirm this would discharged the condition. Please note the monitoring described should be implemented throughout the projects.
Conditions requested: monitoring described should be implemented throughout the projects