14 September 2007 · Director of Planning and Building Control (M. I. McCauley)
Isle Of Man Education, Peel Clothworkers School, Derby Road, Peel, Isle Of Man, IM5 1hp
The proposal involved forming two pedestrian entrances: one western access linking the public highway to the school footpath, and one eastern access through an earth sod bank to the school footpath. This was intended to enhance safe movement of pupils and separate pedestrian from vehicular traffic at the school site.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer assessed the proposal as an improvement to existing pedestrian access arrangements at the school, with no adverse impacts on the surrounding area.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved drawings
This permission relates to drawings SC856/P/20, SC856/P/21 and covering letter all submitted and date stamped 5th June 2007.
Pedestrian barrier
Prior to completion, the applicant shall install a pedestrian barrier at the proposed pedestrian access points to prevent children from running straight out of the accesses into the carriageway.
Do not oppose subject to condition for pedestrian barrier installation
Recommended for approval
Note received regarding underground cables/overhead lines; no objection to proposal