6 February 2007 · Planning Committee
Ballacallin, Lane From Dalby Road To Ballacallin, Dalby, Isle Of Man, IM5 3bt
The proposal involves converting an existing redundant stone barn on the seaward side of the A27 coastal highway between Glen Maye and Dalby into a private dwelling with a garage. Amendments from the previous refused scheme (06/00229/B) include a patio area over a mono-pitch roof on the west elevation replacing a large…
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer noted this is a resubmission amending the scheme previously approved under PA 03/01783/B (valid until May 2009), which was refused in PA 06/00229/B due to a two-storey extension not qualif…
Renovation of Buildings in the Countryside
Requires barn conversions to involve only essential facilities without significant changes to the building's character. Officer assessed amendments as minor (patio, garage extension) not compromising provisions, unlike prior refusal for two-storey element; garage matches materials/roof design.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved plans
This approval relates to drawing numbers 03/2409/2; 1A; 3E; 4D submitted as part of this application and date stamped 27th November 2006.
Access surfacing
Prior to the occupation of the residential unit, the access road must be surfaced and finished as indicated on the drawing 03/2409/4 (D) submitted and date stamped 27th November 2006.
Demolition limits
It is only permitted to demolish and rebuild those parts of the elevations which have been shown on drawing number 03/2409/4 (D) to be rebuilt.
Method statement
Prior to the commencement of works, a method statement must be submitted to and approved by the Planning Authority which demonstrates how the existing structure is to be supported before and during construction.
Roof materials
The roof(s) must be finished in dark natural slate.
Stonework materials
The exterior stonework must be of a traditional nature. NOTE: Split stone on a backing render is not acceptable as an external finish. All existing and proposed stonework must be retained as such and must not be rendered, painted or similarly treated.
Doors and windows
All doors and windows must be timber framed.
No replacement doors/windows
Notwithstanding the provisions of the Town and Country Planning (Permitted Development) Order 2005 (or any Order revoking or re-enacting that Order) no external doors, roof lights or windows shall be replaced (other than those expressly authorised by this permission).
No further development
Notwithstanding the provisions of the Town and Country Planning (Permitted Development) Order 2005 (or any Order revoking or re-enacting that Order) no extensions, garages, garden sheds, conservatories, walls, shall be erected (other than those expressly authorised by this approval).
No surface water to foul sewer
There must be no discharge of surface water to the main foul sewer.
Foul sewer connection
The proposed development must be connected to the main foul sewer. NOTE: A Drainage Connection Fee will be payable to the Drainage Authority on this development.
No objection subject to conditions on foul sewer connection, no surface water to foul sewer, protection of public sewer
no objection subject to inclusion of an informative note on water connection
Much better design than before. No objection.
no objection although wind and solar energy generation should be included
Do not oppose subject to sight lines of 2m by 60m