8 September 2006 · Planning Committee
Palace Hotel & Casino, Palace Buildings, Central Promenade, Douglas, Isle Of Man, IM2 4na
The proposal involves enclosing an existing gas-fired CHP unit (3m x 6.3m x 3.8m high) within a new rendered blockwork structure (8.5m x 4.3m x 4m high) with lean-to roof on the northern boundary of the Hilton Hotel, adjacent to Palace View Terrace, to provide electricity and hot water.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer assessed visual appearance and residential amenity as key issues. Visually, the enclosure improves the site's appearance compared to the existing exposed unit, is screened by a substation …
Time limit
The development hereby permitted shall commence before the expiration of four months and be concluded within eight months from the date of this notice.
Approved drawings
This approval relates to the submitted documents and drawings 2.1538.03, 2.1538.05 and 2.1538.06 all received on 3rd April 2006.
Noise compliance demonstration
Prior to any further operation of the Combined Heat and Power Unit, the applicant must demonstrate to the Department on site that it can be operated such as to comply with the criteria set out in the Schedule attached hereto.
no objection
do not oppose
no objection subject to no surface water discharge to foul sewers
not objecting but seek planning conditions for maximum allowable noise levels measured at certain points with action if non-compliant