28 January 2009 · Acting Senior Planning Officer (delegated under Article 3(13) of the Town and Country (Development Procedure) Order 2005)
Air Quality Monitor Station, Richmond Hill Transmitter Building, Richmond Hill, Douglas, Isle Of Man, IM2 3ap
National Grid Wireless proposed installing two equipment cabinets, each 800mm x 1.4m (height unknown), at the base of an existing 40m lattice telecommunications mast on a site zoned for Government or Service Department Purposes.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The site is an established telecommunications mast site zoned as an Area for Government or Service Department Purposes on the 2005 Area Plan, with existing cabins and apparatus from multiple operators…
General Policy 3
Permits development outside zoned areas for location-dependent development in connection with provision of necessary services. Officer assessed the cabinets as ancillary to the existing mast site, fitting exception (e), with no landscape harm.
Environment Policy 1
Protects countryside from adverse development unless overriding national need with no alternative. Proposal accepted as it would not adversely affect the countryside due to screening and colouring, on established site.
Environment Policy 2
Mentioned as relevant but not specifically assessed in detail.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved plans
This permission relates to the installation of equipment cabinets as shown in drawing numbers 18843_00_004_01, 18843_30_150_M08_08, 18843_30_160_M08_08 and 18843_30_100_M08_08 date stamped 11th April 2008.
Colour coating
Within one month of the installation of the equipment cabinets hereby approved, they shall be colour coated in full accordance with the approved details. Any replacement or modification shall be colour coated to match within one month of being carried out.
Removal if redundant
In the event of the equipment cabinets erected under this approval becoming redundant it must be taken down and removed from the site within 3 months of cessation of use.