26 March 2007 · Delegated - Director of Planning and Building Control (M. I. McCauley)
Isle Of Man Education, Rushen Primary School, Church Road, Port St. Mary, Isle Of Man, IM9 5lw
The proposal is for a small covered waiting shelter at Rushen Primary School to provide sheltered facilities for pupils, located to the east of the school buildings within the site curtilage. It measures just over 7.5m by 3m and 2.7m high, resembling a typical bus shelter and level with the playground for disabled acce…
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer noted the site is designated as Primary School on the 1982 Development Plan Order, with a history of approvals for school alterations and extensions.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved drawings
This permission relates to the erection of a sheltered waiting area as shown in drawings reference CAP 03 and -04 both received on 9th February, 2007.
No objections
No objections (implied by officer report)
Rushen Parish Commissioners have no objections to the covered waiting area at Rushen Primary School. MEA initially requested cable diversion or relocation but later confirmed 2m clearance would suffice with conditions, and Fire Service required consultation under the Fire Precautions Act.
Key concern: underground cable which runs directly under the proposed site of the waiting area
Rushen Parish Commissioners
No ObjectionNo objections
Manx Electricity Authority
Conditional No ObjectionMEA require that either the cable is diverted or the waiting area be relocated clear of any cables.; MEA will not accept liability for any costs incurred for the above.
Conditions requested: either the cable is diverted or the waiting area be relocated clear of any cables; All work is to be carried out with reference to Health & Safety Guidance Note HS(G)47
Manx Electricity Authority
Conditional No Objectionyou will be moving the structure at 2 metres away from the 11,000 volt cables (we require a 2 metre safety clearance from HV Cable for any mechanical excavation)
Conditions requested: moving the structure at 2 metres away from the 11,000 volt cables; All work to be carried out in accordance to GS6 and all the completed application forms for the diversions submitted
Isle Of Man Fire And Rescue Service
No CommentApplicant to consult with the Fire Safety Department as this type of property falls within the scope of the fire Precautions Act 1975
Conditions requested: Applicant to consult with the Fire Safety Department as this type of property falls within the scope of the fire Precautions Act 1975