Andreas Airfield
Braust Farm Andreas Lezayre Isle of Man
DATE: 1st December 2006
PREPARED BY: CH2M HILL
CH2MHILL
CABLE & WIRELESS ISLE OF MAN REF: 91 Andreas Airfield CABLE & WIRELESS
Cable and Wireless Isle of Man Limited (C & W) have recently been awarded an Isle of Man (IOM) Mobile Operators License issued by the Island's Communications Commission to provide a mobile phone network and service to the Island's inhabitants and visitors. This service will compete with the incumbent operator (Manx Telecom) and will allow greater choice and competition for the consumers.
The Mobile phone network will consist of a number of sites that have a combination of equipment, such as panel antenna that provide coverage in the vicinity and also transmission dishes that link sites together and with others in the wider network to provide continuous coverage throughout the Island.
Where possible C&W will endeavour to install their equipment on existing infrastructure or radio transmitters. The aim always is to minimise the visual impact of providing this new mobile phone network.
Where this is not possible and it is necessary to introduce additional telecommunications infrastructure onto the Island this supporting statement will justify, both why the infrastructure is required and demonstrates that the best possible available site has been identified keeping visual amenity as a priority at all times.
It will also help to explain the decisions which led to the specific location being chosen and what alternatives were discounted.
A variety of supporting information may be included with each application but ultimately the C&W aim is to minimise the number of new structures and the overall visual impact of the network whilst providing sufficient signal strength to provide coverage for customers to take advantage of the C&W services that will become available.
The proposed development will consist of a 17.15m monopole mast with 3 no. panel antenna and 2 no. 300mm diameter dishes placed upon it. There will also be 2 no. equipment cabinets, and 1 no. electricity meter cabinet located at ground level. The mast and equipment cabinets shall be enclosed by a 1.25m high timber rail fence. The equipment cabinets, monopole, antennas, and dishes will be finished in green (suggested BS No 4800 12C39 or alternative to be controlled by condition) to match the nearby telecoms tower already in situ.
Full details can be seen on the General Arrangement Drawings that accompany this application.
Our proposal is to locate close to an existing Manx Telecom monopole that is situated approximately 30m away to the East and has a very similar design to the one we are proposing.
The proposed development site is to be located between the edge of a small airfield and the A17 in an area of disused grassland. The location of the site has been strategically considered to provide significant coverage along the nearby A roads, in particular the A9 the A19 and A17, and surrounding settlements in particular Andreas.
Whilst the site provides good coverage to the target area it has also been chosen from a visual amenity perspective as it is located adjacent to a very similar structure currently used by Manx Telecom the surrounding vegetation affords screening of the ground based cabinets The precedent for telecoms to a degree has already been set at this general location as a Manx telecom monopole is already in place approximately 30m to the west of the proposed site, and we are proposing to mirror their design as far as practicable.
Within this search area, there are no existing dedicated telecom sites or suitable existing structures on which to mount the antennas, apart from the existing Manx Telecom site which is a single user monopole. We feel by redeveloping this structure into one that would be able to accommodate the equipment of both operators, we would create a structure that would be significantly taller and more bulky which in turn would be more visually intrusive than two single user monopoles.
We also looked at a disused electricity pole at Kimmeragh farm approx 1kn east of the proposed site. This was discounted as we would need to get a height of approximately 25 meters to make the location work from a coverage perspective for us. Due to the prominent position on a hillside we felt that a pole of this size in this spot was more visually intrusive.
As a result, we feel the best choice of site location for a new mast would be in direct colocation with the existing Manx Telecom site. We believe any alternative sites within the area would be more exposed, and in closer proximity to residential properties. Therefore it is felt that by colocating with the existing Manx Telecoms site, the best possible location has been identified.
We have met on several occasions with Ian Brooks to discuss various proposals, including this site. Mr Brooks has accepted the need for sites such as this and was supportive of choosing a location with least visual impact. He said that the merits of the scheme can be considered in more detail upon submission of the formal planning application and drawings.
At the request of the planning officer, we have included an additional elevation plan in order to demonstrate the appearance of the site from the South as well as the West.
We believe that the only planning history in relation to telecommunications in this area was the adjacent Manx Telecom Monopole which was approved and now in occupation. We are proposing to utilise a very similar design as this will minimise the visual impact of the development, and keep the design of telecom sites in this area consistent.
Cable and Wireless do not have any existing sites on the Isle of Man. In order to provide coverage to potential customers in and around Andreas and the surrounding roads a site is needed in this area.
If this location is not supported, there will still be a need for site in this area, and we feel the very best location has already been identified by way of this application. Without a site in this area, many residents, businesses, and tourists will not be able take advantage of having a choice of Mobile Operator the issuing of new licences was (in part) designed to accommodate.
The accompanying coverage plots provide good evidence of what coverage this site provides and how it fits in with other proposed sites in the wider network.
The location of the site has been carefully considered so the cabin will be very well screened by, or in the backdrop of the adjacent vegetation.
As mentioned in Section 4 we have located adjacent to an existing very similar structure as we feel the visual amenity will not be significantly affected due to the fact that we are co locating.
Where practicable, the design features of the Manx Telecom site has been emulated to ensure the design and appearance of telecommunications sites in this location is consistent. Accordingly, the mast, equipment cabin, antennas, and dishes are all to be painted green shades appropriate to the surrounding trees and vegetation.
The pole has been chosen to be further away from the nearest residential property than the existing mast to minimise any visual impact to the single dwelling.
The positioning of the site in this location is critical to ensure both continuous coverage to the main roads, to residential areas, and local businesses, and to maintain line-of-sight between it and the adjacent planned sites for the dish links.
Planning Scheme Development Plan Provisional Order, 1982:
The proposed site does not have a specific or restrictive designation under the 1982 Development Plan, nor does it fall within an area of restricted building height due to Air Safety.
Draft Strategic Plan, November 2004:
We have reviewed the draft strategic plan in order that we adhere to the requirements and directives contained therein wherever possible.
The following was particularly noted:
1.6.1 “where unusual matters arise, or where there is no Manx guidance, it will often be appropriate and helpful to have regard to legal judgements or advice published in the UK or the EU”.
In cases where there is no clear guidance we have followed the UK best practice as outlined in PPG8.
It was evident from the 6 main strategic aims looking at maintaining ‘Quality of Life’ then there must be a balance between economic progress in the pursuit of “manageable and sustainable growth” 2.3(2) and the need “to protect and improve the quality of the environment” 2.3(4)
This is further highlighted as follows:
3.3 (d) - “to protect the individual character of and identity of settlements and to identify and protect those green spaces in built areas which contribute positively to public amenity”.
3.4 (c) - “to safeguard and provide for the needs and aspirations of existing and new location dependant businesses”.
Within the transport and Communications section it states:
3.5 (h) – “to ensure that the island is well served by modern telecommunications without compromising the protection of our landscape”.
Finally within Transport Infrastructure and Utilities:
11.9.2 – “It is important that a balance be struck between the need for new evolving
telecommunications systems to satisfy residential and business demand and the impact that the necessary infrastructure will have on the environment. Measures which may help to achieve a satisfactory balance will include a presumption against visually intrusive masts in sensitive landscapes, the encouragement of mast sharing by different operators and the removal of redundant infrastructure. Exceptions to this policy would need to demonstrate a strategic national need which cannot be otherwise secured by mast sharing or alternative locations.
The inspector's comments were also viewed in relation to the draft plan.
Policies in EP1-3 set out protective policies for the countryside. Development which would have an adverse effect on the character and appearance of the landscape within the existing designated areas will not be permitted. In these areas the protection and conservation of the landscape will be the most important consideration. However development will be permitted where;
In all cases during the search and planning consultation we have endeavoured always to compromise our technical requirements with the need to reduce visual impact of the proposed development by best use of design and location.
We believe that the design and location have been carefully considered in this instance and we also believe we have demonstrated the importance of this site to give vital coverage. This therefore forms an important part of this 'national need' to provide the Isle of Man with a competitive mobile network.
This site has been designed in accordance with the current mainland UK Cellular operators guidance for both Occupational & Public ICNIRP compliance. Our design consultants are satisfied that this site design complies with the above guidelines and therefore a signed ICNIRP certificate is enclosed with this application.
1) Isle of Man Government Statutory Boards, Offices & Agencies Plans 2006-2009. Volume 3.
Page 25, under Communications Commission Aims & Objectives Section:
Objective: Social inclusion – To enhance access to services for the whole population:
"We will enforce universal service obligations by telecoms operators with significant market power. They must provide telephone services throughout the Island, ...".
To summarise, we consider that this is the optimum location and design for our proposed site.
The coverage plots help to demonstrate that there is a definite need for the site both as a vital link site to adjacent cells and providing important coverage to Andreas and the surrounding A roads.
The siting and appearance has been carefully considered to provide the least visual impact possible and we are best utilising the existing foliage as screening.
Therefore the design proposed represents both the optimum planning/environmental and technical solution in this instance. As such, we believe the development as proposed is in accordance with planning guidance as defined above.