24 November 2006 · Director of Planning and Building Control (delegated under Article 3(13) of the Town and Country (Development Procedure) Order 2005)
Shangri-La, 19, Cannan Avenue, Kirk Michael, Isle Of Man, IM6 1hf
The proposal involves adding a pitched roof extension projecting 5 metres to the rear and 3.3 metres wide to a single-storey detached bungalow. Additional works include re-tiling the existing roof, removing chimney stacks, and applying smooth render to the external walls.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer assessed the proposed pitched roof extension (5m rear projection, 3.3m width) and found it acceptable due to its height, siting, and size, leaving a 2.7m gap to the boundary shared with ne…
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved plans
This approval relates to the submitted documents and drawing KT/1/06 all received on 29th September 2006.
Obscure glazing
Obscure glazing (Grade 5) shall be installed in the North elevation of the en-suite window and shall be kept and maintained thereafter.
Do not oppose
No objection
No objection in principle subject to no discharge of surface water to foul drainage
Manx Electricity Authority, Drainage Division, and Michael Commissioners all responded with no objection to application 06/01661/B, with Drainage Division and MEA requesting specific conditions.
Key concern: Underground Cables/Overhead Lines present in the area
Manx Electricity Authority
Conditional No ObjectionThere are Underground Cables/Overhead Lines present in the area indicated in you Planning Application. Please contact Anthony Kinrade or Ian Horsey, Operations and Maintenance Dept, Network Services, Manx Electricity Authority, (Tel. 687705) to discuss working practices around Cables and Overhead Lines which may be required to be diverted before any work can be carried out on site.; Contact the M.E.A. for Electrical Site Safety 5 documents, (Tel. 687766), before any work is carried out on site. All work to be carried out with reference to Health and Safety Executive Guidance Notes HS(G)47 & GS6.
Conditions requested: a condition of planning be that the applicant must contact the Authority
Drainage Division
Conditional No ObjectionNO OBJECTION in principle subject to the following conditions; There must be NO discharge of surface water (directly or indirectly) from this proposed development to any foul drainage system(s) so as to comply with the requirements of the Department of Transport Drainage Division and the Sewerage Act 1999.
Conditions requested: There must be NO discharge of surface water (directly or indirectly) from this proposed development to any foul drainage system(s) so as to comply with the requirements of the Department of Transport Drainage Division and the Sewerage Act 1999.
Michael Commissioners
No ObjectionNO OBJECTION