Officer Planning Report Recommendations
Planning Report And Recommendations {{table:124071}} {{table:124072}} {{table:124073}} {{table:124074}} ### Considerations ### Written Representations ### Consultations
Officer's Report
Description Of Application Site
- The application site is the new prison site which is currently under construction at Jurby Airfield.
Proposal
- The proposal is to install a temporary septic tank
- The tank will hold 9000 litres.
Relevant Planning History
- 03/00575 – Construction of a new Category B Prison including perimeter security wall, fencing, landscaping, car park and access – granted 24.08.2004
Development Plan Policies
- Isle of Man Planning Scheme (Development Plan Order) 1982
Statutory Consultation Responses
- Jurby Parish Commissioners – No objection
Public Responses
- Press notice were posted on 07/12/05
- No representations have been received.
Issues
- Proposal is to a temporary septic tank to serve the temporary toilet facilities on the construction site. The septic tank will be removed on completion of the new prison
- The proposal does not impact on anybody or any watercourses.
Conclusion
I therefore recommend that permission be granted subject to conditions in the attached schedule.
Recommendation
Recommended Decision: Permitted
Date of Recommendation: 20.02.2006
Conditions and Notes for Approval / Reasons and Notes for Refusal
C: Conditions for approval N: Notes attached to conditions R: Reasons for refusal O: Notes attached to refusals
C 1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.
C 2. This permission relates to the installation of a temporary septic tank as shown in drawing numbers Ex (9-) 077; Ex (9-) 078 date received 7th December 2005 and Fax from McGarrigle & Jackson dated 9th December 2005
C 3. Within 1 month of the completion of the new prison, the septic tank shall be removed from the site.
I confirm that this decision accords with Government Circular Nos 44/05 (Delegation of Functions to Director of Planning and Building Control) and 47/05 (Delegation of Functions to Senior Planning Officer)
Decision Made: Permitted Date: 21.02.2006
Signed: M.I. McCauley Director of Planning and Building Control