Officer Planning Report Recommendations
Planning Report And Recommendations {{table:118816}} {{table:118817}} {{table:118818}} {{table:118819}} ### Considerations {{table:118820}} ### Written Representations ### Consultations {{table:118821}} ### Policy
Officer's Report
The planning application seeks approval for the construction of a ramp to the front of a property in Laxey and its extension to accommodate a lift shaft.
There are no objections to the planning application. DAFF have recommended that the works to accommodate the lift shaft be restricted to either April, May, September or October so as to prevent harm to the local resident bat population. I recommend that the planning application be approved.
Recommendation
Recommended Decision: Permitted
Date of Recommendation: 04.12.2005
Conditions and Notes for Approval / Reasons and Notes for Refusal
C : Conditions for approval N : Notes attached to conditions R : Reasons for refusal
- : Notes attached to refusals
C 1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.
C 2. This approval relates to drawing no.s BS:5024/01, BS:5024/02, BS:5024/04, BS:5024/05 and BS5025:SL1 date stamped the 25th October 2005.
C 3. In order to prevent harm to the native bat population works required in relation to the accommodation of the lift shaft may only be undertaken in either April, May, September or October in any one year.
N 1. The applicant is advised to contact the Fire Safety Officer to discuss the provision of appropriate fire precaution measures.
I confirm that this decision accords with Government Circular No 57/01 (Delegation of Functions to Director of Planning and Building Control).
Decision Made : Approval by delegation Date : 5/12/05
Signed: [Handwritten signature] M. I. McCauley Director of Planning and Building Control