29 December 2004 · Planning Committee
Land To Rear Of The Colby Pump Main Road Colby Isle Of Man
The proposal was for a single dormer bungalow and detached single-storey garage on a wooded site allocated in the Arbory and East Rushen Local Plan as Development Area 13 for one dwelling. The site is to the rear of the Colby Pump on Main Road, Colby, in a residential area.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The Planning Committee initially approved the application on 10 December 2004 subject to conditions protecting trees, ensuring privacy via obscure glazing and fencing, and connecting to foul sewer.
Arbory and East Rushen Local Plan Development Area 13
Site allocated for single dwelling with retention/protection of existing deciduous trees and consultation with DAFF. Officer and agent confirmed compliance as proposal is for one dormer bungalow and garage in SE corner, with tree survey showing no major losses and conditions for protection.
no comments to make / no further comments
no adverse traffic impacts
no objection subject to connection to public foul sewer and no surface water to foul sewer
complies with local plan Development Area 13, tree consultations satisfactory, privacy addressed by conditions
Statutory consultees from Transport (Drainage and Highways) and DAFF (Wildlife, Conservation, Forestry) raised no objections subject to drainage conditions and wildlife/tree protections, while multiple neighbouring residents strongly objected citing loss of privacy, amenity, bat habitat impacts, and non-central siting.
Key concern: Adjacent pipistrelle bat roost requiring retention of feeding habitat
Transport Drainage Division
Conditional No ObjectionNO OBJECTION In principle subject to:; A Communication Fee will be payable to the Department of Transport in respect of this drainage connection.
Conditions requested: Proposed development must be connected to the public foul sewer in a manner acceptable to the Department of Transport Drainage Division and on terms and conditions agreed PRIOR to commencement of building works. All drainage works must conform to Manx Sewers for Adoption with inspections/surveys including CCTV at developer’s expense.; NO discharge of surface water from proposed development to any foul drainage system(s) per Sewerage Act 1999.; Applicant to supply copy of Building Control Application for surface water discharge
DoT Highways Division
No ObjectionNo adverse traffic impacts.
Wildlife and Conservation Division
Conditional No ObjectionThe site lies adjacent to a roost of pipistrelle bats, so it is important that the feeding habitat on the application site is not lost.; If a house were agreed, then an appropriate curtilage should be identified.
Conditions requested: Retain boundary trees and mix of trees/glades for bat foraging; Retain ivy on site (may be controlled but not removed); Identify appropriate curtilage and retain woodland
Forestry Division
No ObjectionThe proposed development shouldn't necessitate the removal of any of the larger trees on the site, particularly those on the perimeter.; The indicated location is probably the least damaging in terms of the tree cover.