Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Kinrade Associates Limited Stella Maris Mountain Road
Ramsey
Isle of Man
IM8 2JJ
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Mr & Mrs Leslie Neilson Proposal: Erection of a replacement dwelling at: Ballalonna
Dalby
Isle of Man
IM5 3BW
which was considered on 16th April 2009, subject to compliance with the conditions specified below. Date of Issue: 16th April 2009 Murray House Mount Havelock
Douglas
Deputy Secretary Planning
Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the erection of a replacement dwelling, Ballalonna, Dalby, Patrick, as shown by the plans 2422/2, SM09/185/2 and SM09/185/3 all received 11th February 2009.
- The roof(s) must be finished in natural slate.
- Notwithstanding the provisions of the Town and Country Planning (Permitted Development) Order 2005 (or any Order revoking or re-enacting that Order) no extensions, greenhouses,
09/00204/8
walls, gates, fences, garden sheds, summerhouses, flag poles, decking, garages, or tanks for the storage of oil for domestic heating shall be erected (other than those expressly authorised by this approval.)
- The external walls shall be finished in rough cast render and retained as such thereafter.
- All external windows and doors shall be of timber construction and must remain as such thereafter.
- The sod bank/hedge to the north of the approved replacement dwelling shall be constructed during the first planting season following the completion of the development and in accordance with the guidance set out within Planning Circular 1/92 "Manx Hedges".
This decision was made by the Senior Planning Officer in accordance with the authority delegated to her under Article 3(13) of the Town and Country (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;