17 May 2010 · Senior Planning Officer (delegated under Article 3(13) of the Town and Country (Development Procedure) Order 2005)
Vacant Site Opposite Jck Ltd, Port Way, Balthane Industrial Estate, Ballasalla, Isle Of Man, IM9 2aj
The proposal involves constructing a portal frame warehouse building of 675 sq. m floor area with associated office and ancillary accommodation, plus 14 car parking spaces, on a vacant plot in the Balthane Industrial Estate.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The proposed development accords with the prevailing land use for the area as the site lies within an area designated as Industrial on the Town and Country Planning (Development Plan) Order 1982 and d…
Parking Standards for New Residential Development
Requires one parking space per 50 sq. m of floor area for industrial development. The proposal provides 14 spaces for 675 sq. m, exceeding the requirement. Condition 4 requires future additional floors to address further parking needs per this standard.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved plans
This permission relates to the erection of an industrial building with associated parking, as shown in drawings WL/10/1153/1, WL/10/1153/2 and WL/10/1153/3 all received on 26th March, 2010.
Materials approval
The cladding must match that on the existing building to the north east or otherwise be approved by the planning authority prior to the application of any external finish to the building.
Future development restrictions
Any proposal for the creation of further floorspace through the introduction of additional floors within the building must be the subject of further planning approval before being implemented and such proposal must address the need for the provision of further vehicular parking to accommodate the additional floorspace in accordance with the requirements of the Strategic Plan (Appendix Seven).
Do not object
Does not object to this application
No Objection subject to conditions on connection to public sewer, no surface water to foul drainage, and restriction to dry industrial processes
Highways Division, Water & Sewerage Authority Drainage Division, and Malew Parish Commissioners all raised no objection to application 10/00433/B, with the Water Authority requesting specific drainage conditions.
Department of Infrastructure Highways Division
No ObjectionThe Department of Infrastructure Highways Division does not object to this application
Isle of Man Water & Sewerage Authority Drainage Division
Conditional No ObjectionNo Objection subject to the following conditions; it is an offence under Manx legislation to permit the discharge of polluting or harmful matter to any public sewers or watercourses.
Conditions requested: The proposed dwelling must be connected to the public sewer(s) in a manner acceptable to the Isle of Man Water & Sewerage Authority. All drainage works must conform to the requirements of the Authorities "Manx Sewers for Adoption" and all necessary inspections/surveys [including CCTV] are to be carried out at the developer's expense.; There must be NO discharge of surface water (directly or indirectly) from this proposed development to any foul drainage system(s) so as to comply with the requirements of the Isle of Man Water & Sewerage Authority, Drainage Division and the Sewerage Act 1999.; The use of the proposed units must be restricted to dry industrial processes only. The only discharges which will be accommodated in the public foul sewer at this time are domestic (only) sewage from WCs and canteens.; Under section 4(3) of the Sewerage Act 1999 the applicant must give 21 days notice, in writing, to the Drainage Division, prior to making any communication to the public sewer.
Malew Parish Commissioners
No ObjectionThey do not object to this application.