31 March 2023 · Delegated - Principal Planner (Jason Singleton)
Manx Telecom (Engineering), Greenhill Communication Centre, Isle Of Man Business Park, Douglas, Isle Of Man, IM2 2qz
Manx Telecom applied to replace the current non-illuminated sign at the site entrance with a new dark blue narrow vertical box sign featuring illuminated logos and text for 'Manx Telecom' and 'Data Centre'. The site is within the industrial area of the Isle of Man Business Park.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The key considerations were the impact on the character and streetscene of the industrial area and highway safety. The proposed illuminated signage is simplistic and would not negatively impact the ch…
General Policy 2
GP2 (b)(g)(i)(m)(n) requires development to respect character, amenity, highway safety, and be in suitable locations. The officer assessed the signage's simplistic design and business-related content as not harming the industrial area's character or streetscene, with no highway impact, fully complying.
General Policy 6
GP6 relates to design and external appearance. The narrow vertical dark blue box with illuminated logos was deemed simplistic and acceptable, not negatively impacting the building or streetscene.
Time limit
The advertisement(s) hereby granted consent shall be begun before the expiration of four years from the date of this notice. Reason: To avoid the accumulation of unimplemented advertisement consents.
does not oppose this application; no significant negative impact upon highway safety, network functionality and/or parking
Highway Services HDC and Braddan Parish Commissioners both confirmed no significant negative highway impacts and no objections to application 23/00121/D for replacement signage at Greenhill Data Centre.
Highway Services HDC
No ObjectionAfter reviewing this Application, Highway Services HDC finds it to have no significant negative impact upon highway safety, network functionality and /or parking.
Highway Services HDC
No ObjectionAfter reviewing this Application, Highway Services HDC finds it to have no significant negative impact upon highway safety, network functionality and/or parking.
Braddan Parish Commissioners
No ObjectionThe Commissioners discussed the following planning applications at their meeting held on 9 March 2023 and I can confirm that they had no objections to either of the applications listed below:-; PA23/00121/D - Replacement of existing non-illuminate signage with new LED illuminated signage at site entrance - Greenhill Data Centre, IOM Business Park, Braddan, IM2 2QZ