Loading document...
Cromptons Architectural Design & Project Management Services 21 Stanley Road Peel Isle Of Man IM5 1NP
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Mr & Mrs John & Sophie Kneen, Ref 22/01450/B, for the Demolition of former cattle shed and existing store, erection of extension and conversion of existing barn into living accommodation for tourist and residential use at Ballaoates Farm Ballavagher Road St Johns Isle Of Man IM4 3JE.
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
areas shall not be used for any purpose other than the parking and turning of vehicles associated with the development and shall remain free of obstruction for such use at all times.
Reason: To ensure that sufficient provision is made for off-street parking and turning of vehicles in the interests of highway safety.
Reason: To ensure proper control of the development and to avoid any future undesirable fragmentation of the curtilage.
Reason: To ensure that the development is only used and occupied as short-let holiday accommodation during the holiday season.
NOTE Allowing surface water runoff onto a public highway would contravene Section 58 of the Highway Act 1986 and guidance contained in section 11.3.11 of the Manual for Manx Roads.
NOTE Bats are listed on Schedule 5 of the Wildlife Act 1990; they are protected by law and it is an offence to:
intentionally or recklessly kill, injure or take a bat intentionally or recklessly damage or destroy, or obstruct access to, any structure or place
which bats use for shelter or protection
intentionally or recklessly disturbs any bat while it is occupying a structure or place which it uses for that purpose. The maximum penalty that can be imposed is a fine up to 10,000 pounds.
NOTE FOR YOUR INFORMATION Please be aware that a ban on the installation of fossil fuel heating systems in any new building(s) and or extension(s), will come into force on 1st January 2025.
You therefore are encouraged to ensure that your proposed development includes alternatives to fossil fuel heating systems if you believe that such works will not be completed by that date.
To this end, if you propose an alternative, such as air source or ground source heat pump(s), or any other heating system that would require planning approval, the details of this should be addressed now. This may require you to resubmit your planning application to accommodate the alternative permitted heating system proposed.
This decision has been made for the following reasons(s) The conversion of the existing building and proposed built extension would not adversely impact upon the visual amenities of the countryside setting and landscape and have no impacts upon private or public amenities and therefore comply with General Policy 3b, Environment Policy 1,2, 16 and Business Policy 11,12,14 of the IOM Strategic Plan.
Date of Issue: 26th May 2023
Director of Planning and Building Control
Guidance Note
This decision was made by the Planning Committee in accordance with the authority delegated to it.
This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer’s report and any correspondence which led to the assessment and decision is available to view on the Government’s website (via Online Services www.gov.im/Viewapplications) or at the Department’s offices Murray House, Mount Havelock, Douglas.
Implementation The decision does not become final until either Any appeal has been concluded; or 21 days have passed since the date on this notice and no appeal has been submitted
Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain: the grounds for making the appeal; payment of the planning appeal fee (currently £335); and
if relevant, confirmation that the appellant wishes to have the appeal determined by means of an inquiry and payment of the additional inquiry fee (currently £125). Where the appeal is submitted by the applicant they must:
specify in detail and by reference to material planning considerations the reasons why the appellant disagrees with that determination; and
Where against a refusal, on the grounds of deficient detail or supporting documentation, set out why they consider the information or documentation forming part of the application was sufficient in the circumstance. If the appeal is submitted by someone who has interested Person Status but is not listed in Article 4(2) of the Development Procedure Order 2019, that person must relate their grounds for making the appeal to issues which they included in representations made prior to the application being determined.
Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated.
An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department’s website www.gov.im/planningappeal
If this decision becomes final because there is no appeal, the Department’s public reference copy (counter copy) of the planning application (should one have been received) may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.