Creation of off road parking land to rear MEA Substation Lhargan Port St Mary
Do not oppose subject to the imposition of the following condition
The access drive arrangements shall comprise a turning facility to permit a motor car to turn around within the site so that a vehicle can emerge from the site in a forward gear
08/02244/REM
Reserved matters application for the erection of a detached dwelling with integral garage land between 3 Summerland and Parsonage Road, Summerland, Ramsey
Objection
The proposed access does not meet the required visibility standards onto Parsonage Road. The Highways Department recommend that the existing access onto Summerland Road be used for this development
08/02242/B
Demolition of existing garages and erection of a dwelling (comprising amendments to PA 08/00584B) garages between 32&33 Mill St, rear of 33 Hope St, Castletown
Do not oppose Note: Previous objection overruled by Planning Department
Rheynn Arraghey
Director of Highways B W Hannay BSc (Hons) M Sc, C Eng, MICE, FIHT, CMILT, C DipAF Highways Division Sea Terminal Building Douglas, Isle of Man IM1 2RF Switchboard (01624) 686600 Telephone (01624) 686676 Fax (01624) 686677 Email: [email protected]
Isle of Man
Government
The Secretary, Planning Committee Department of Local Government and the Environment, Murray House, Douglas.
Contact: John Kneen Our ref: Wgek 18/12/08 Your ref: Wgek 18/12/08
23 December 2008
Dear Sirs,
Planning Application
PA 08/2242/B – Demolition of existing garages and erection of a dwelling (comprising amendments to PA 08/00584B), Garages Between 32 & 33 Mill Street To Rear Of 33 Hope Street, Castletown.
The Drainage Division of the Department of Transport has assessed the above planning application and would like to submit the following comments to your Planning Committee.
No Objection subject to the following conditions:-
The proposed dwelling must be connected to the public sewer(s) in a manner acceptable to the Department of Transport Drainage Division. All drainage works must conform to the requirements of the Department of Transport’s “Manx Sewers for Adoption” and all necessary inspections/ surveys [including CCTV] are to be carried out at the developer’s expense.
In accordance with the Sewerage Act 1999, a communication fee will be payable to the Department of Transport in respect of this property being connected (directly or indirectly) to the public drainage system.
Note: Under section 4(3) of the Sewerage Act 1999 the applicant must give 21 days notice, in writing, to the Drainage Division, prior to making any communication to the public sewer. The applicant is therefore advised to contact the Development Control section of the Division to discuss this matter.
There must be NO discharge of surface water (including that from roofs and paved areas) from this proposed development to any foul drainage system(s) so as to comply with the requirements of the Department of Transport Drainage Division and the Sewerage Act 1999.
The application states that the surface water from the proposed development is to be discharged to the “existing drainage”. If this “existing drainage” discharges (directly or indirectly) to the foul sewerage system then it should be noted that an alternative means of surface water disposal must be provided.
Cont:
Cont:
In the event that these applications are approved I should be grateful if these comments could be incorporated in the approval notices.
Yours faithfully,
John Kneen
John Kneen Development Control Technician.