19 September 2008 · Director of Planning and Building Control (delegated under Article 3(13) of the Town and Country (Development Procedure) Order 2005)
6, The Chase, Ballakillowey, Colby, Isle Of Man, IM9 4bl
Mrs D H Harrington applied to install four solar collectors (Solfex high performance evacuated tube collectors, each 1500mm by 300mm) on the roof of her bungalow: two on the front (east) elevation and two on the rear (west).
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer assessed that the proposed solar collectors would comply with the general encouragement of renewable energy equipment as set out at paragraph 12.2.8 of the Strategic Plan.
Isle of Man Strategic Plan para 12.2.8
The policy at paragraph 12.2.8 of the Strategic Plan provides general encouragement for renewable energy equipment. The officer tested the solar panels against this, confirming compliance due to their small scale on a bungalow roof. No tensions noted as panels cause no visual or other harm.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved plans
This permission relates to the installation of solar collection equipment as shown and described in the drawings and plans received on 28th July, 2008.
No objections