Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Quay Design Ltd. 5 The Quay Port St Mary IM9 5EA
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Rev Wesley McDowell Proposal: Erection of an extension to create ancillary living accommodation to rear elevation and an open porch to front elevation at: Port Erin Gospel Church Castletown Road Port Erin Isle Of Man IM9 6BD
which was considered on 6th September 2007, subject to compliance with the conditions specified below.
Date of Issue: 10th September 2007
Murray House Mount Havelock Douglas
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This permission relates to the extension of the church building as shown in drawing 1309-01 and -02 both received on 9th July, 2007, to provide accommodation for those visiting the Port Erin Gospel Church and where no individual period of occupation exceeds two weeks in length.
Reason for condition: the proposed accommodation is smaller in floor area than that which would satisfactorily accommodate occupants on a permanent basis. Furthermore, the accommodation has limited amenity space and outlook. As such the accommodation should not be used for permanent occupation.
NOTE PRIOR to the commencement of any works the applicant is advised to consult the Chief Fire Officer to ensure that adequate fire precautions are taken.
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/dlge/planning/plan
Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.