Registered Building Approval Notice
The Town and Country Planning (Development Procedure) Order 2005 The Registered Building Regulations 2005
STQS The Studio Eairy Ranch Arassey Road Glen Maye IM5 3BY In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Mrs Patricia Wild Proposal: Registered Building consent to form new internal doorway between entrance lobby and reception room, RB Nos. 152 at: 6 Auckland Terrace Parliament Street Ramsey Isle of Man IM8 1AF which was considered on 4th February 2010, subject to compliance with the conditions specified below.
Date of Issue: 5th February 2010 Murray House Mount Havelock Douglas
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the following submitted documents and drawings:
Existing floor plans P07 06503 Rev O date stamped 13 Aug 2009 Site Location Plan annotated 'Plan A' date stamped 13 Aug 2009
A4 detail sheet including 'Architrave Elevation - scale 1/20' and Architrave Section - Scale $1 / 5^{\prime}$ date stamped 13 Aug 2009 A4 detail sheet including 'New stud wall and cornice junction - scale 1/10' and 'Overlayed ambulant steps - Scale 1/10' date stamped 13 Aug 2009 A4 detail sheet entitled 'Ground Floor rev b' date stamped 13 Aug 2009.
This decision was made by the Senior Planning Officer under the authority delegated by the Department under Regulation 4(2) of the Registered Building Regulations 2005.
Guidance Note
This permission refers only to that required under the Registered Building Regulations 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;