10 September 2009 · Director of Planning and Building Control (delegated authority)
Factory, School Road, Onchan, Isle Of Man, IM3 4pb
The proposal involves relocating the existing bicycle shed from the southern elevation to the north-western corner of the industrial site and erecting a new lean-to skip shelter in its place along the southern elevation.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The officer considered the skip shelter to be relatively modest in scale and design, in keeping with the character of the adjoining industrial building, with limited impact on the amenity of the surro…
Light Industrial Use designation
The site is located within an area of Light Industrial Use. No specific policies in Planning Circular 1/2000 or Isle of Man Strategic Plan were considered material. The industrial zoning supports the ancillary structures without policy conflict.
Time limit
The development hereby permitted shall commence before the expiration of four years from the date of this notice.
Approved drawings
This approval relates to the submitted Drawings P. 970 SS/01 and P. 970 SS/02 both date stamped as received on 20th July, 2009.
recommend that the application be APPROVED for planning purposes only
Do not oppose has no traffic management, parking or road safety implications
No Objection subject to conditions: no discharge of surface water to foul drainage; if existing drainage connects to foul, provide alternative
Drainage Division has no objection subject to conditions on surface water discharge; Highways Division does not oppose due to no traffic implications; Onchan District Commissioners recommend approval.
Key concern: Surface water discharge to foul drainage systems prohibited; alternative disposal required if existing drainage connects to foul sewers
Drainage Division, Department of Transport
Conditional No ObjectionNo Objection subject to the following conditions; The application states that the surface water from the proposed development is to be discharged to the "existing drainage"
Conditions requested: There must be NO discharge of surface water (including that from roofs and paved areas) from this proposed development to any foul drainage system(s) so as to comply with the requirements of the Department of Transport Drainage Division and the Sewerage Act 1999
Highways Division
No ObjectionDo not oppose has no traffic management, parking or road safety implications
Onchan District Commissioners
SupportThe Commissioners recommend that the application be APPROVED for planning purposes only