Peel WWTW - Planning Condition Responses
C16.River Neb
No work shall be undertaken adjacent to the River Neb other than in accordance
with a scheme to limit potential impacts on the River’s fish population, which
scheme shall previously have been submitted to and approved in writing by the
Department.
Reason: In order to protect aquatic habitat and species pursuant to Environment
Policy 8 of the Strategic Plan.
Response
Please refer to documents attached which contain method statements and
approvals following discussions with DEFA Fisheries:
RSTS Peel - Section 18, Precast Head Wall
RSTS Peel - Section 18, Mill Race - Pipe Crossings
PCS-HS-MS - Peel RSTS - River Neb & Mill Race - 24.01.25
S 18 consent MUA Peel STW-Mill Race IF105WR-ME250307
S 18 consent MUA Peel STW-Head Wall IF105WR-ME250307