13 June 2025 · Delegated - Principal Planner (Jason Singleton)
11, Slieau Whallian Park, St. Johns, Isle Of Man, IM4 3jh
The application is for a Certificate of Lawful Development confirming that a roof light at the property has been installed without planning permission for more than 4 years, making it immune from enforcement.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The principal test for a Certificate of Lawfulness is whether, on the balance of probabilities, the breach of planning control (installation of the roof light without permission) occurred more than 4 …
Evidence confirmation
There is sufficient evidence demonstrating that the rooflight has been in situ since 2010.