Mr Chris Millar 23 West Quay Ramsey IM8 1DL
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Third Man Properties, Ref 25/00053/CON, for the Registered building consent for the demolition elements proposed within application 25/90052/B at Stanley Hotel West Quay Ramsey Isle Of Man IM8 1DW .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with paragraph 2(2)(a) of schedule 3 of the Town and Country Planning Act 1999 and to avoid the accumulation of unimplemented registered building consents.
This decision relates to the following plans and drawings, date stamped received on 15 January 2025:
24183001 - Site & Location Plan 24183002 - Ground & First Floor Survey Drawing 24183003 - Second Floor & Elevations Survey Drawing 24183004 - Ground & First Floor Proposal Drawing 24183005 - Second Floor & Elevations Proposal Drawing 24183006 - Sections and 3D images This decision has been made for the following reasons(s) The proposal meets the statutory tests within Section 18 of the Town and Country Planning Act 1999, as the character of the conservation area is being preserved. It is also judged that the application meets the tests of Environment Policy 39 of the IOM Strategic Plan 2016 as the
proposed development will preserve the character and appearance of the Conservation Area. The application is therefore judged to be acceptable.
Date of Issue: 30th April 2025 J CHANCE
Building Control
This decision was made by a Principal Planner in accordance with the authority delegated to them. This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer's report and any correspondence which informed the assessment and decision is available to view on the Government's website (via https://pbc.gov.im/online-applications/)
The decision does not become final until either
Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain:
Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated. An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department's website www.gov.im/planningappeal If this decision becomes final because there is no appeal, the Department's public reference copy (counter copy) of the planning application (should one have been received) may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.