Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Kelly Lewthwaite Building Design 23 Market Street Douglas IM1 2PA
In pursuance of powers granted under the above Act and Order the Department of Infrastructure does hereby APPROVE the following application made on behalf of:
Name: J C Properties Ltd Proposal: Erection of a warehouse building with associated office and car parking at: Plot 4, Opposite Entrance To JCK Depot Port Way Balthane Industrial Estate Ballasalla Isle Of Man
which was considered on 21st November 2011, subject to compliance with the conditions specified below. Date of Issue: 22nd November 2011 Murray House Mount Havelock Douglas
Mrs C Dudley Deputy Secretary to the Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- and car parking as proposed in the submitted documents and drawings WL/11/1211/1, WL/11/1211/2 and WL/11/1211/3 all received on 10th October 2011.
- The cladding must match that on the existing building to the north east or otherwise be approved by the planning authority prior to the application of any external finish to the building.
- Any proposal for the creation of further floorspace through the introduction of additional floors within the building must be the subject of further planning approval before being implemented and such proposal must address the need for the provision of further vehicular
parking to accommodate the additional floorspace in accordance with the requirements of the Strategic Plan (Appendix Seven).
This decision was made by the Development Control Manager in accordance with the authority delegated to her under Article 3(13) of the Town and Country (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/transport/planning/plan/applications/decision.xml
Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.