**Document:** DEC Decision Notice
**Application:** 20/00921/D — Erection of illuminated totem entrance signs and non-illuminated directory signs and building numbering signs
**Decision:** Permitted
**Decision Date:** 2020-11-05
**Parish:** Michael
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/13439-michael-jurby-ind-estate-industrial-signage/documents/999909

---

# DEC Decision Notice

Public Estates & Housing Division Department Of Infrastructure Sea Terminal Building Douglas IM1 2RF

TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Control of Advertisements) Regulations 2013

In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Public Estates & Housing Division, Ref 20/00921/D, for the Erection of illuminated totem entrance signs and non-illuminated directory signs and building numbering signs at Jurby Ind Estate Jurby Industrial Estate Jurby Isle Of Man .

Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).

- 1. The advertisement(s) hereby granted consent shall be begun before the expiration of four years from the date of this notice. Reason: To avoid the accumulation of unimplemented advertisement consents.
- 2. Prior to the installation of any totem a detailed design of the totem is required to be submitted and approved in writing by the Department and this approved scheme is required to be fully adhered to. Reason: In the interest of the visual amenities of the area.

This approval relates to the submitted documents and drawings 101, 102, 103, 104 and 105 all received on 12th August 2020.

This decision has been made for the following reasons(s) It is considered that the proposal would comply with General Policies 2, 6, 7 & 8 of the Isle of Man Strategic Plan 2016.

Date of Issue: 5th November 2020

Director of Planning and Building Control

Guidance Note

This decision was made by the Head of Development Management in accordance with the authority delegated to them.

This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.

A copy of the Officer’s report and any correspondence which led to the assessment and decision is available to view on the Government’s website (via Online Services www.gov.im/Viewapplications) or at the Department’s offices Murray House, Mount Havelock, Douglas.

Implementation The decision does not become final until either Any appeal has been concluded; or 21 days have passed since the date on this notice and no appeal has been submitted

Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.

Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.

Appeal Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain: the grounds for making the appeal; payment of the planning appeal fee (currently £285); and

if relevant, confirmation that the appellant wishes to have the appeal determined by means of an inquiry and payment of the additional inquiry fee (currently £100).

Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated.

An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department’s website www.gov.im/planningappeal

If this decision becomes final because there is no appeal, the Department’s public reference copy (counter copy) of the planning application may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/13439-michael-jurby-ind-estate-industrial-signage/documents/999909*