**Document:** Planning Approval Notice 08/00635/B
**Application:** 08/00635/B — Erection of a corporate office headquarters with associated access road, parking and services
**Decision:** Permitted
**Decision Date:** 2008-06-11
**Parish:** German
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/85022-german-opposite-ai-centre-access/documents/1567148

---

# Planning Approval Notice 08/00635/B

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Mr Ashley Pettit
4 Osborne Terrace
Douglas
IM1 3LH

In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Department Of Agriculture, Fisheries & Forestry
**Proposal:** Erection of a corporate office headquarters with associated access road, parking and services
**at:** Site Opposite A.I. Centre
Foxdale Road
St Johns
Isle Of Man

which was considered on 30th May 2008, subject to compliance with the conditions specified below.

**Date of Issue:** 11th June 2008

Murray House Mount Havelock Douglas

Secretary to the Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the construction of a corporate office headquarters, as indicated on the plans and information submitted as part of this application and date stamped 26th March 2008.

3. Prior to the commencement of the development, details of the height and design of the lighting columns, together with details in relation to the hours of use, must be submitted to the Planning Committee for consideration and approval.

**NOTE** The applicant is requested to maintain pedestrian access to the site during and after construction of the office building hereby approved.

NOTE The Department of Transport Highways Division request that details of the surface water outfall be provided for consideration prior to the start of construction. In addition, any works that are associated with the river requires consent under the Land Drainage Act 1934; such approval must be obtained prior to the start of construction on site.

NOTE The proposed building must be connected to the public sewer(s) in a manner acceptable to the Department of Transport Drainage Division. A communication fee will be payable to the Department of Transport in respect of such a connection. The applicant is advised to consult with the Development Control Section of the Division to discuss all aspects of the development.

This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.

---

### Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/dlge/planning/plan/applications/decision.xml

Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---