**Document:** Planning Approval Decision Notice
**Application:** 07/02297/B — Removal of a chimney stack
**Decision:** Permitted
**Decision Date:** 2008-02-25
**Parish:** Braddan
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/84477-braddan-kewaigue-school/documents/1519186

---

# Planning Approval Decision Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Department of Education Works Division
Unit 15
Snugborough Trading Estate
Union Mills
Braddan
IM4 4LH

In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Department of Education Works Division
**Proposal:** Removal of a chimney stack
at:
Kewaigue School
Kewaigue
Douglas
Isle of Man
IM2 1QH

which was considered on 19th February 2008, subject to compliance with the conditions specified below.

**Date of Issue:** 25th February 2008

Murray House
Mount Havelock
Douglas

Deputy Secretary Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This permission relates to the removal of a chimney stack as shown in drawing number KS/01 and photograph date stamped 13th December 2007; Letter from the Department of Education Works Division dated 11th December 2007.

3. The void must be slated over using slates to match those on the existing roof.

4. The works may take place only after the end of August, and must be completed before the end of April; the roof space may not be entered other than during this period.

NOTE These requirements are necessary to avoid disturbing the bats which roost and breed within the brickwork of the stack below the roof line; the applicant is advised to consult the Wildlife and Conservation Officer of the Department of Agriculture, Fisheries and Forestry (tel.843109) before commencing any works. 26

This decision was made by the Senior Planning Officer in accordance with the authority delegated to her under Article 3(13) of the Town and Country (Development Procedure) Order 2005.

### Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/dlge/planning/plan/applications/decision.xml

Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---