**Document:** Planning Approval Notices
**Application:** 06/01777/R — Retention of new track
**Decision:** Permitted
**Decision Date:** 2007-03-19
**Parish:** Lezayre
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/81745-lezayre-glen-auldyn-retention-track/documents/1481629

---

# Planning Approval Notices

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Highways Division
Network Planning
Department Of Transport
Sea Terminal Building
Douglas
Isle Of Man

In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:

**Name:** Glen Auldyn Sporting Syndicate
**Proposal:** Retention of new track
**at:** Glen Auldyn
Ramsey
Isle Of Man

which was considered on 8 March 2007, subject to compliance with the conditions specified below.

**Date of Issue:** 14th March, 2007
**Murray House Mount Havelock Douglas**

Secretary Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the submitted documents and drawing 06 0103/1 all received on 16th October 2006.

This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to down load from the Department’s website www.gov.im/dlge/planning/plan

You should note that a copy of the Officer’s report which led to the decision being made, along with any correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Penketh - Millar
1 Dale Street
Ramsey
Isle Of Man
IM8 1BJ

In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Glen Auldyn Sporting Syndicate
**Proposal:** Retention of new track
**at:** Glen Auldyn
Ramsey
Isle Of Man

which was considered on 8 March 2007, subject to compliance with the conditions specified below.

**Date of Issue:** 19th March, 2007
**Murray House Mount Havelock Douglas**
*(Signature)*

Secretary Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the submitted documents and drawing 06 0103/1 all received on 16th October 2006.

This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to down load from the Department’s website www.gov.im/dlge/planning/plan

You should note that a copy of the Officer’s report which led to the decision being made, along with any correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/81745-lezayre-glen-auldyn-retention-track/documents/1481629*