**Document:** Planning Approval Decision Notice
**Application:** 06/01646/B — Extension to create workshop units, infilling between approved units
**Decision:** Permitted
**Decision Date:** 2006-11-07
**Parish:** Malew
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/81493-malew-land-opposite-portside-extension/documents/1478542

---

# Planning Approval Decision Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Arch-Tec (IOM) Ltd
The Architectural Studio
Stanley House
Lord Street
Douglas
IM1 2BF

In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Fields Park Ltd
**Proposal:** Extension to create workshop units, infilling between approved units
**at:**
Land Opposite Portside Units 2 And 3
Balthane Industrial Estate
Balthane
Ballasalla
Isle Of Man

which was considered on 3 November 2006, subject to compliance with the conditions specified below.

**Date of Issue:** 7 November, 2006
**Murray House Mount Havelock Douglas**
*(Signature: Murray House Mount Havelock, 1906, with a signature)* ☐
**Secretary Planning Committee**
*(Signature: Secretary Planning Committee, 2006)*

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This permission relates to the erection of further units and the creation of further car parking spaces all as shown in drawing reference AT 653.6 received on 26th September, 2006.

3. The proposed units must be finished to match the existing units on the site.

4. The use of the proposed units must be restricted to dry industrial processes only.

NOTE: for clarification, the only discharges which will be accepted into the public foul sewer at this time are domestic sewage from wcs and canteens. If in the future the sewerage system is capable of accommodating anything further and the Department of Transport are satisfied that this is the case, a further application may be made to vary this condition or to propose a specific process which does not comply with this condition.

5. There must be no discharge of surface water to the main foul sewer.

6. The proposed development must be connected to the main foul sewer.

NOTE: A Drainage Connection Fee will be payable to the Drainage Authority on this development

NOTE The applicant is advised to contact the M.E.A. Planning Department (Tel. 687781), to discuss the electricity supply for this application.

This decision was made by the Director of Planning and Building control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to down load from the Department’s website www.gov.im/dlge/planning/plan

You should note that a copy of the Officer’s report which led to the decision being made, along with any correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---