**Document:** Planning Approval Review 18 November 2005
**Application:** 04/02575/B — Refurbishment and alterations to existing building, former Pipe
**Decision:** Permitted
**Decision Date:** 2005-09-19
**Parish:** Lonan
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/77459-lonan-factory-tent-road-refurbishment-alterations/documents/1433178

---

# Planning Approval Review 18 November 2005

## Town and Country Planning Acts, 1934 - 1991

[Table omitted in markdown export]

### Isle of Man Planning Scheme (Development Plan) Order 1982

McGarrigle & Jackson
19 Mount Havelock
Douglas
IM1 2QG

In pursuance of powers granted under the above Acts and Order the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Department Of Trade & Industry
**Proposal:** Refurbishment and alterations to existing building, former Pipe
at: Factory
Tent Road
Laxey
IM4 7DB

which was considered on 11 November 2005, subject to compliance with the conditions specified below.

Date of Issue: 18 November, 2005
Murray House
Mount Havelock
Douglas

Secretary Planning Committee
*(Signature)*

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to drawing no. P01 date stamped the 13th December 2004 and drawing no. P03 rev. B date stamped the 9th March 2005.

3. The use of the building shall not commence until details of a minimum of 20 dedicated car parking spaces have been submitted to and agreed with the Planning Authority. These car parking spaces should be located within Shore Road Car Park.

4. There must be no discharge of surface water (including that from roofs and paved areas) from the development to any foul drainage system(s).

NOTE The applicant/developer is recommended to consult with the Fire Safety Officer with regard to the provision of appropriate fire precautions measures.

This review has been considered by the Planning Committee on written evidence. Any additional submissions not previously circulated to interested parties are enclosed herewith.

Note 1: This permission refers only to that required under the Town and Country Planning Acts and does not include any consent or approval under any other enactment, bylaw, order or regulation.

Note 2: No works may be commenced until such time as -
- the time for requesting an appeal in relation to the decision has expired; or
- any appeal has been completed.

Note 3: Rights of the appeal against the decision of the planning committee are attached.

Note 4: An appeal must be requested within a period of 21 days.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*