**Document:** Planning Approval Decision Notice
**Application:** 09/01063/B — Temporary storage of infill material
**Decision:** Permitted
**Decision Date:** 2009-08-18
**Parish:** Malew
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/63357-malew-field-number-420855/documents/1380413

---

# Planning Approval Decision Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Isle Of Man Water Authority
Drill Hall
Tromode
Douglas
IM2 5PA
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:

Name:
Proposal:
at:

Isle Of Man Water Authority
Temporary storage of infill material
Field Number 420855
Ballagawne Road
Ballabeg
Castletown
Isle Of Man
which was considered on 14th August 2009, subject to compliance with the conditions specified below.

Date of Issue: 18th August 2009

### Murray House <br> Mount Havelock <br> Douglas

Deputy Secretary Planning Committee

### Schedule Of Conditions:

1. This permission relates to the storage of material generated from the excavation of the adjacent field for the creation of the reservoir approved under PA 09/0107, as shown in drawings 1101A, 1102A and 1103A all received on 23rd June, 2009.
2. The material may be stored as approved for a period not exceeding twenty four months following the commencement of works on the new reservoir approved under PA 09/0107 after which time the material must be removed from the site and the original profile of the field restored.

NOTE The applicant is encouraged to commence preparation of plans for the backfilling of the existing reservoir and restoration of that site as soon as possible to prevent any delay in the final removal of the excavated material from site.

NOTE The applicant is also recommended to liaise with the Manx Electricity Authority in respect of the proximity of the overhead electricity lines to the south and working practices around this supply.

This decision was made by the Director of Planning and Building Control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005.

## Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml

Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;

- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/63357-malew-field-number-420855/documents/1380413*