**Document:** Planning Approval Notice
**Application:** 10/00537/R — Installation of two solar panels (retrospective)
**Decision:** Permitted
**Decision Date:** 2010-06-04
**Parish:** Braddan
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/36238-braddan-manderley-vicarage-road-solar-panels-retrospective/documents/1351998

---

# Planning Approval Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Kelly Lewthwaite Building Design
23 Market Street
Douglas
IM1 2PA
In pursuance of powers granted under the above Act and Order the Department of Infrastructure does hereby APPROVE the following application made on behalf of:

Name: Mr Tom Maher
Proposal: Installation of two solar panels (retrospective)
at: Manderley
Vicarage Road
Douglas
Isle Of Man
IM2 2QG
which was considered on 25th May 2010, subject to compliance with the conditions specified below.

Date of Issue: 4th June 2010

### Murray House <br> Mount Havelock <br> Douglas

Mrs C Dudley
Deputy Secretary to the Planning
Committee

### Schedule Of Conditions:

1. This permission relates to the retention of two solar panels as shown in drawing numbers WL/09/1131/3A, WL/09/1131/4A and WL/09/1131/2A date stamped 16th April 2010.

This decision was made by the Senior Planning Officer in accordance with the authority delegated to her under Article 3(13) of the Town and Country (Development Procedure) Order 2005.

## Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml

Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;

- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*