**Document:** Onchan Commissioners Response
**Application:** 13/00323/B — Installation of two doors to replace existing windows
**Decision:** Permitted
**Decision Date:** 2013-04-18
**Parish:** Braddan
**Document Type:** consultation / local_authority_response
**Source:** https://planningportal.im/a/4162-braddan-g-e-aviation-factory-school-windows-replacement/documents/1289929

---

# Onchan Commissioners Response

ALL COMMUNICATIONS TO BE ADDRESSED TO THE CHIEF EXECUTIVE/CLERK

## Onchan District Commissioners

**BARRANCEE ARDJUN CHONNAGNYN** P. M. Hulme, CEnv IEng MIWO - Chief Executive/Clerk and Commissioner for Oaths Main Road, Onchan, Isle of Man, IM3 1RD

Administration and Finance: Tel: (01624) 675564 email: admin@onchan.org.im Surveyors and Works: Tel: (01624) 624967 email: surveyors@onchan.org.im Fax: (01624) 663482

Our ref: BTP/AW

9th April 2013

The Secretary
Planning Committee
Department of Infrastructure
Murray House
Mount Havelock
DOUGLAS
IM1 2SF

Dear Sir,

Re: PA 13/00323 - Installation of two doors to replace existing windows, GE Aviation Factory, School Road, Onchan

I am directed to advise you that the above application was considered by the Onchan District Commissioners at their meeting held on Monday 8th April 2013.

The Commissioners recommend that the application be APPROVED for planning purposes only.

Yours faithfully,

**B T PRICE**

**DISTRICT SURVEYOR**

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/4162-braddan-g-e-aviation-factory-school-windows-replacement/documents/1289929*