**Document:** Planning Approval Decision Notice
**Application:** 13/00156/C — Additional use of dwelling as holiday accommodation
**Decision:** Permitted
**Decision Date:** 2013-03-20
**Parish:** Malew
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/3996-malew-ballagawne-farm-dwelling/documents/1288542

---

# Planning Approval Decision Notice

## Isle of Man
### Government

*Reitige Elian Vanne*

---

**Quay Design Ltd.**

5 The Quay

Port St Mary

IM9 5EA

---

### Town and Country Planning Act 1999

#### The Town and Country Planning (Development Procedure) Order 2005

---

On 19th March 2013, and in pursuance of powers granted under the above Act and Order, the Department of Infrastructure determined to **APPROVE** planning application **13/00156/C** by Mr David Cooil for the additional use of dwelling as holiday accommodation at Ballagawne Farm, Ballagawne Road, Ballabeg, Castletown, Isle Of Man IM9 4PD subject to compliance with the following conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the additional use of dwelling as holiday accommodation as proposed in the submitted documents and drawings 1600-01, 1600-02 and 1600-03 all received on 6th February 2013.

3. Prior to the occupation of any of the approved guest rooms, the five on-site parking spaces as shown on the proposed site plan (drawing 1600-01) are to be completed and retained thereafter.

---

**Date of Issue:**

20th March 2013

*M Gallayher*

**Director of Planning and Building Control**

---

### Guidance Note

This decision was made by a Senior Planning Officer in accordance with the authority delegated to them. This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005. Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

---

*Continued overleaf*

---

An appeal form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/transport/planning/plan/applications/decision.xml

Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, are available for inspection at the Department.

The proposed development must not be commenced until either;

- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.
If no appeal is lodged within 21 days of the date of issue overleaf, and this decision becomes final, the Department's public reference copy (counter copy) of the planning application may be collected by the applicant or their agent from Murray House.

Please note that if the counter copy of the application is not collected within THIRTY DAYS following the last date on which a planning appeal can be made it will be destroyed without further notice.

Department of Infrastructure, Murray House, Mount Havelock, Douglas, Isle of Man, IM1 2SF Tel (01624 685950) email; planning@gov.im
$13 / 00156 / \mathrm{C}$

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/3996-malew-ballagawne-farm-dwelling/documents/1288542*