**Document:** Planning Approval Decision Notice
**Application:** 12/01608/B — Conversion of existing offices on upper floors onto three apartments
**Decision:** Permitted
**Decision Date:** 2013-01-29
**Parish:** Lezayre
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/3744-lezayre-31-parliament-conversion/documents/1285291

---

# Planning Approval Decision Notice

Arch-Tec (IOM) Ltd
The Architectural Studio
2nd Floor
20 Duke Street
Douglas
IM1 2AY

## Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

On 28th January 2013, and in pursuance of powers granted under the above Act and Order, the Department of Infrastructure determined to **APPROVE** planning application **12/01608/B** by Fistard Property Investments Limited for the conversion of existing offices on upper floors onto three apartments at 31 Parliament Street Ramsey Isle Of Man IM8 1AT subject to compliance with the following conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the location plan and drawing nos 1153.1, 1153.2, 1153.3 and 1153.4 date stamped the 5th December 2012.

Date of Issue:
29th January 2013

M Gallagher
Director of Planning and Building Control

### Guidance Note

This decision was made by the Planning Committee in accordance with the authority delegated to it. This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005. Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

An appeal form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/transport/planning/plan/applications/decision.xml

Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, are available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

If no appeal is lodged within 21 days of the date of issue overleaf, and this decision becomes final, the Department's public reference copy (counter copy) of the planning application may be collected by the applicant or their agent from Murray House.

Please note that if the counter copy of the application is not collected within THIRTY DAYS following the last date on which a planning appeal can be made it will be destroyed without further notice.

Department of Infrastructure, Murray House, Mount Havelock, Douglas, Isle of Man, IM1 2SF Tel (01624 685950) email; planning@gov.im

12/01608/B

---