**Document:** Planning Approval Decision Notice
**Application:** 11/00849/B — Erection of a dwelling
**Decision:** Permitted
**Decision Date:** 2011-11-03
**Parish:** Braddan
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/1195-braddan-land-forming-part-new-build-dwelling/documents/1250837

---

# Planning Approval Decision Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Matt Slader
MJS Planning & Design
First Floor
Handel House
Somerset Place
Teignmouth
TQ14 8EP

In pursuance of powers granted under the above Act and Order the Department of Infrastructure does hereby **APPROVE** the following application made on behalf of:

**Name:** Mr David Gibson
**Proposal:** Erection of a dwelling
**at:** Land Forming Part Of
14 Main Road
Onchan
Isle Of Man
IM3 1AS

which was considered on 2nd November 2011, subject to compliance with the conditions specified below.

**Date of Issue:** 3rd November 2011

Murray House
Mount Havelock
Douglas

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to drawing no.s 0002 rev. B, 0003 rev. B, 0004 rev. B, 0009 rev. A (x2), 0010 rev. A and 0011 rev. A date stamped the 27th September 2011.

3. Prior to the commencement of development details of finished floor levels of the dwelling must be submitted and agreed by the Planning Authority.

4. The residential curtilages of the proposed dwelling and existing dwelling are hereby defined by the red lines shown on drawing no. 0009 rev. A date stamped the 27th September 2011.

This decision was made by the Development Control Manager in accordance with the authority delegated to her under Article 3(13) of the Town and Country (Development Procedure) Order 2005.

---

### Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/transport/planning/plan/applications/decision.xml

Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---