**Document:** Planning Approval Decision Notice
**Application:** 11/00542/B — Erection of a replacement dwelling (retrospective) (Amendments to PA 09/01978/B & PA 04/01353/B)
**Decision:** Permitted
**Decision Date:** 2011-06-24
**Parish:** Lezayre
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/890-lezayre-sarah-s-cottage-replacement-dwelling/documents/1247570

---

# Planning Approval Decision Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

Penketh - Millar
23 West Quay
Ramsey
Isle of Man
IM8 1DL

In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Infrastructure does hereby **APPROVE** the following application made on behalf of:

**Name:** Mr & Mrs Timothy Rand
**Proposal:** Erection of a replacement dwelling (retrospective) (Amendments to PA 09/01978/B & PA 04/01353/B)
**at:** Sarah's Cottage
Cornaa
Ramsey
Isle of Man
IM7 1EQ

which was considered on 17th June 2011, subject to compliance with the conditions specified below.

**Date of Issue:** 24th June 2011

Murray House
Mount Havelock
Douglas

Mrs P Faragher
Deputy Secretary to the Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the erection of a replacement dwelling (Amendments to PA 09/01978/B & PA 04/01353/B) as proposed in the submitted documents and drawings 10 726 06 and 10 726 01 all received on 14th April 2011.

3. Within one month of the decision notice full details of both hard and soft landscaping works are required to be submitted to and approved in writing by the Planning Authority and these works shall be carried out as approved. Details of the soft landscaping should

include, but not be limited to, details of planting along the eastern boundary, albeit set back from the visibility splays. Details of the hard landscaping works include footpaths and hard surfacing materials. The hard landscaping works shall be completed in full accordance with the approved details prior to the first occupation of the proposed dwelling hereby permitted. All planting shall be carried out in accordance the approved details in the first planting and seeding seasons following that first occupation. Any trees or shrub which within 5 years from the completion of the development dies, is removed or becomes seriously damaged or diseased shall be replaced in the next planting season with another of similar size and species unless the planning authority gives written consent to any variation.

4. Notwithstanding the provisions of the Town and Country Planning (Permitted Development) Order 2005 (or any Order revoking or re-enacting that Order) no extensions, greenhouses, walls, gates, fences, garden sheds, summerhouses, flag poles, decking, roof lights, windows, garages, or tanks for the storage of oil for domestic heating shall be erected (other than those expressly authorised by this approval).

5. The subcills must be pre-formed concrete cills to a depth of 0.15m and the windows all timber framed sliding sashes all as shown in the approved drawing.

6. Within one month of this approval all extensions and roof lights not approved under this application are to be removed in accordance with drawing 10 726 07.

7. The use of the attic/roof space is restricted to the storage of domestic items only; no approval is hereby given for the use of the attic space for any type of living accommodation.

This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.

### Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/transport/planning/plan/applications/decision.xml

Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

## Planning Committee 17/06/11

### Erection of a replacement dwelling (retrospective) (Amendments to PA 09/01978/B & PA 04/01353/B) - Sarah's Cottage, Cornaa, Ramsey - 11/00542/B

After discussion the Planning Committee accepted the recommendation but requested the additional Conditions:-

C6. Within one month of this approval all extension and roof lights not approved under this application are to be removed in accordance with drawing 10 726 07

C7. The use of the attic/roof space is restricted to the storage of domestic items only; no approval is hereby given for the use of the attic space to be used for any type of living accommodation.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/890-lezayre-sarah-s-cottage-replacement-dwelling/documents/1247570*