**Document:** Officer Planning Report
**Application:** 06/00080/B — Creation of a covered store to front garden and extension of existing parking area to create an additional parking space.
**Decision:** Permitted
**Decision Date:** 2006-05-24
**Parish:** Arbory
**Document Type:** report / officer_report
**Source:** https://planningportal.im/a/80096-colby-main-road-extension/documents/1217450

---

# Officer Planning Report

## Planning Report And Recommendations [Table omitted in markdown export] [Table omitted in markdown export] [Table omitted in markdown export] [Table omitted in markdown export] ### Considerations [Table omitted in markdown export] ### Written Representations ### Consultations [Table omitted in markdown export]

### Officer's Report

#### The Site

The site represents the domestic curtilage of an existing dwelling which lies on the northern side of the Main Road (A7) through Colby. The site has a frontage to the main road of 12m and is 23m in depth.

#### Planning Status

The site lies within an area of white land on the Arbory and East Rushen Local Plan which was approved by Tynwald in 1999.

## Planning History

PA 88/0764 proposed the creation of a vehicle hardstanding - permitted

## The Proposal

Proposed here is the extension of the existing hardstanding to accommodate three vehicles side by side and the erection of a store behind the parking area. this store is to be at the same height as the existing flat area to the front of the house although there will now be concrete balustrading which looks a little out of keeping with the traditional property in front of which it will sit.

## Assessment

Beside the balustrading, the proposal is not unacceptable in visual terms and Department of Transport indicate that they have no objection subject to the lowering of the roadside wall to promote better visibility.

## Party Status

Arbory Parish Commissioners, Department of Transport Drainage Division, Department of Transport Highways and Traffic Division, Manx Electricity Authority are statutory authorities and as such should be afforded party status in this instance.

### Recommendation

Recommended Decision: Permitted

Date of Recommendation: 19.05.2006

### Conditions and Notes for Approval / Reasons and Notes for Refusal

C : Conditions for approval
N : Notes attached to conditions
R : Reasons for refusal
- : Notes attached to refusals

C 1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

C 2. This permission relates to the creation of a covered store and parking facilities all as shown in drawings reference 1158-01 Rev A and -02 received on 28th March and 19th January, 2006 respectively.

C 3. There must be no discharge of surface water to the main foul sewer.

C 4. Prior to the commencement of works on site, the applicant must consult the Manx Electricity Authority regarding the low voltage overhead line which crosses the site.

C 5.

The front boundary wall and pillar to the west of the access must be lowered to 1m in height prior to the commencement of works on site.

I confirm that this decision accords with Government Circular Nos 44/05 (Delegation of Functions to Director of Planning and Building Control) and 47/05 (Delegation of Functions to Senior Planning Officer)

Decision Made : Permitted Date : 22/6/06

Signed :
M. I. McCauley
Director of Planning and Building Control

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/80096-colby-main-road-extension/documents/1217450*