**Document:** Planning Approval Decision Notice
**Application:** 05/01265/B — Erection of a four storey building to form two self contained flats Senior Planner agreed to extension of duration of consent by a further 12 months to 23/10/10 on 21/10/09
**Decision:** Permitted
**Decision Date:** 2005-09-15
**Parish:** Rushen
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/79001-rushen-plot-formerly-3-4-apartment-extension/documents/1211609

---

# Planning Approval Decision Notice

## Town and Country Planning Acts, 1934 - 1991

### Isle of Man Planning Scheme (Development Plan) Order 1982

Mr N Cadwallader
Architectural Services
10 Lime Street
Port St Mary
IM9 5ED

In pursuance of powers granted under the above Acts and Order the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Mr & Mrs J Taylor & Mrs M Gueudre
**Proposal:** Erection of a four storey building to form two self contained flats
**at:** Plot Formerly 3 And 4
The Promenade
Port St. Mary
Isle Of Man

which was considered on 9 September 2005, subject to compliance with the conditions specified below.

**Date of Issue:** 19th September, 2005
**Murray House Mount Havelock Douglas**

Secretary Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This permission relates to the erection of two apartments as shown in drawings JT/28/04/05/2 received on 17th August, 2005 and T/28/04/15/01 received on 6th July, 2005 and JT28/04/05/3 received on 6th September, 2005.

**NOTE** For connections to Flats and Apartments the following apply - "Water Supply to Flats and Apartments - Regulations", and if applicable a "Form Of Undertaking In Respect Of Supply Pipes" will be required. Copies of these documents can be

obtained from the IoMWA or alternatively by contacting the IoMWA Byelaws Inspector (Les Quayle on telephone 695957).

NOTE PRIOR to the commencement of any works the applicant is advised to consult the Chief Fire Officer to ensure that adequate fire precautions are taken.

This decision was made by the Planning Committee constituted in accordance with Paragraph 2 of Schedule 1 of the Isle of Man Planning Scheme (Development Plan) Order 1982.

Note 1: This permission refers only to that required under the Town and Country Planning Acts and does not include any consent or approval under any other enactment, bylaw, order or regulation.

Note 2: No works may be commenced until such time as -
- the time for requesting a review of the initial decision has expired; or
- any review of the initial decision has been completed; or
- the time for requesting an appeal in relation to the decision has expired; or
- any appeal has been completed.

Note 3: Rights of the review of the decision are attached.

---