**Application:** 05/00890/B — Installation of uPVC casement windows to replace existing on rear elevation of tourist units 1 and 3,
**Decision:** Permitted
**Decision Date:** 2005-07-21
**Parish:** Andreas
**Document Type:** report / officer_report
**Source:** https://planningportal.im/a/78547-andreas-ballalheaney-road-windows-replacement/documents/1209919

---

# Officer Planning Report Recommendations

## Planning Report And Recommendations [Table omitted in markdown export] ### Considerations [Table omitted in markdown export] ### Written Representations ### Consultations [Table omitted in markdown export] ### Policy

### Officer's Report

The application site is situated at Ballalheaney to the south of Andreas Road. The application site is currently a complex of building used by tourists. The site is set in the open countryside.

The windows would have the same pattern of sections and glazing bars than the existing windows. The proposed are set on the rear elevation of the buildings. The rear is open countryside with no public thoroughfare. I consider the proposal will not have a negative effect on the appearance of the building and impact on the visual amenities of the area.

In terms of the impact on the street scene of Andreas Road, the extension would be situated approximately 145m away from the public highway. In between is landscaping in the form of trees and shrubs that will obscure any views of the building. I consider the proposal will not cause demonstrable harm to the visual amenities of the street scene.

## Recommendation

Recommended Decision: Permitted

Date of Recommendation: 04.07.2005

### Conditions and Notes for Approval / Reasons and Notes for Refusal

C : Conditions for approval
N : Notes attached to conditions
R : Reasons for refusal
- : Notes attached to refusals

C 1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

C 2. The permission is for the replacement of the existing windows on the rear elevations of building number 1 and 3 as shown on drawing numbers SC901/P/10-101 and SC901/P/10-100 both received on 11th May 2005

I confirm that this decision accords with Government Circular No 57/01 (Delegation of Functions to Director of Planning and Building Control).

Decision Made : Approval by delegation Date: 14/4/05 Signed: [Handwritten signature] M. I. McCauley Director of Planning and Building Control

---