**Document:** Planning Approval Decision Notice
**Application:** 05/00328/B — Erection of a two storey extension to side and single storey extension to rear elevation
**Decision:** Permitted
**Decision Date:** 2005-05-10
**Parish:** Ballaugh
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/77782-ballaugh-5-glebe-aalin-close-extension/documents/1206144

---

# Planning Approval Decision Notice

## Town and Country Planning Acts, 1934 - 1991

### Isle of Man Planning Scheme (Development Plan) Order 1982

Corlett & Kinrade
1 Dale Street
Ramsey
IM8 1BJ

In pursuance of powers granted under the above Acts and Order the Department of Local Government and the Environment does hereby **APPROVE** the following application made on behalf of:

**Name:** Mr & Mrs Borland
**Proposal:** Erection of a two storey extension to side and single storey extension to rear elevation
**at:** 5 Glebe Aalin Close
Ballaugh
Ramsey

which was considered on 26 April 2005, subject to compliance with the conditions specified below.

**Date of Issue:** 10th May, 2005
**Murray House Mount Havelock Douglas**
[Signature: "Pana Galle"]
Secretary Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to drawing no.s 5001/1 and 5001/2 date stamped the 21st February 2005.

3. The external finishes of the extension must match those of the existing building in all respects.

4. There must be no discharge of surface water (including that from roofs and paved areas) from this development to any foul drainage system(s).

This decision was made by the Director of Planning in accordance with powers delegated to him under Paragraph 2 (6) (b) of the Isle of Man Planning Scheme (Development Plan) Order 1982.

Note 1: This permission refers only to that required under the Town and Country Planning Acts and does not include any consent or approval under any other enactment, bylaw, order or regulation.

Note 2: No works may be commenced until such time as -
- the time for requesting a review of the initial decision has expired; or
- any review of the initial decision has been completed; or
- the time for requesting an appeal in relation to the decision has expired; or
- any appeal has been completed.

Note 3: Rights of the review of the decision are attached.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/77782-ballaugh-5-glebe-aalin-close-extension/documents/1206144*