**Document:** Highways Division Response
**Application:** 03/00146/GB — Alterations to re-instate original half timbering to gable outlet
**Decision:** Permitted
**Decision Date:** 2003-06-24
**Parish:** Braddan
**Document Type:** consultation / highways_response
**Source:** https://planningportal.im/a/72992-braddan-rechabite-hall/documents/1183461

---

# Highways Division Response

## Department of Transport

Rheynn Arraghey
Director of Highways
B W Hannay, B.Sc.(Hons), M Sc,C. Eng., MICE
MIHT,C Dip.A.F.

Highways Division
Network Planning
Sea Terminal Building
Douglas, Isle of Man
IM1 2RF
14 MAY 2003
SEPT OF LOCAL GOVERNMENT
AND THE ENVIRONMENT

Secretary to the Planning Committee
Department of Local Government and the
Environment
Murray House
Mount Havelock
Douglas
ISLE OF MAN
IM1 2SF

Date: 6th May 2003

Dear Sir

**Subject - Press Notice** 10th May 2003

The Highways Division of the Department of Transport has no views on the following
application, the application having been considered and having no adverse traffic impacts.

03/0146

Yours faithfully

Ken Hunnorm.

K C ASHCROFT
Network Planning Engineer

---