**Document:** Planning Approval Decision Notice
**Application:** 12/00344/B — Construction of a raised concrete base, surrounding paved hardstanding, footpaths and four flag poles in connection with the proposed memorial site for the Mona's Queen 3 anchor
**Decision:** Permitted
**Decision Date:** 2012-04-17
**Parish:** Rushen
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/2481-rushen-kallow-point/documents/1168850

---

# Planning Approval Decision Notice

## Isle of Man Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) Order 2005

MacOwan Collett
Consulting Engineers Ltd
Ianda House
4 Mona Terrace
Finch Road
Douglas
Isle of Man
IM1 3NA

In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Infrastructure does hereby **APPROVE** the following application made on behalf of:

**Name:** Port St Mary Commissioners
**Proposal:** Construction of a raised concrete base, surrounding paved hardstanding, footpaths and four flag poles in connection with the proposed memorial site for the Mona’s Queen 3 anchor
**at:** Kallow Point
Clifton Road
Port St. Mary
Isle of Man

which was considered on 16th April 2012, subject to compliance with the conditions specified below.

**Date of Issue:** 17th April 2012
**Murray House Mount Havelock Douglas**

Mrs P Faragher
Deputy Secretary to the Planning Committee

### Schedule Of Conditions:

1. The development hereby permitted shall commence before the expiration of four years from the date of this notice.

2. This approval relates to the construction of a raised concrete base, surrounding paved hardstanding, footpaths and four flag poles in connection with the proposed memorial site for the Mona’s Queen 3 anchor as proposed in the submitted documents and drawings PA/01, PA/02, PA/03 and PA/04 all received on 5th March 2012.

3. Prior to the commencement of works, samples of the proposed paving to be used in the development must be submitted to and approved by the Planning Authority. The development shall be carried out in accordance with the approved details.

This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.

---

### Guidance Note

This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.

Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.

A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department’s website www.gov.im/transport/planning/plan/applications/decision.xml

Please note that a copy of the Officer’s report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.

The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*