**Document:** Planning Statement of Case 27 Feb 2
**Application:** 23/00063/B — Variation of condition 2 of 14/00689/C - to allow sharps storage in 20 x 20ft storage containers and to include other projects such as highway, drainage and flood alleviation works. Variation of condition 3 - for sharps storage for a period of up to December 2026 and projects until end of January 2028.
**Decision:** Permitted
**Decision Date:** 2025-05-21
**Parish:** Braddan
**Document Type:** report / planning_statement
**Source:** https://planningportal.im/a/55575-braddan-ballakinnish-nurseries-ballakinnish/documents/1100568

---

# Planning Statement of Case 27 Feb 2

Variation of conditions 2 and 3 of PA 14/00689/C to extend the use of land at the former Ballakinnish Nurseries Site as a DOI Highways Depot for a further five years

Planning Statement of Case

Date: January 2025

## Contents

- 1 Introduction.......................................................................................................................................2

- 1.1 Purpose...............................................................................................................................2
- 1.2 Background and Existing Layout.......................................................................................3
- 1.3 Justification for the Continued Use of the Site ..................................................................6
- 1.4 Justification for use as temporary storage for clinical sharps waste..................................7

- 2. Proposal............................................................................................................................................8

- 2.1 Duration & Hours of Normal DoI Operation.....................................................................8
- 2.2 Duration & Hours of Clinical Sharps Waste Operation.....................................................8
- 2.3 Site Security .......................................................................................................................8
- 2.4 Material Storage.................................................................................................................9
- 2.5 Clinical Sharps Waste Storage...........................................................................................9
- 2.6 Vehicle Movements .........................................................................................................10

- 3. Environmental Impact....................................................................................................................10

- 3.1 General.............................................................................................................................10
- 3.2 General Clinical Sharps Waste ........................................................................................11
- 3.3 Noise ................................................................................................................................11
- 3.4 Vibration ..........................................................................................................................12
- 3.5 Water / Soil Pollution.......................................................................................................13
- 3.6 Dust / Air Pollution..........................................................................................................13
- 3.7 Ecology ............................................................................................................................14
- 3.8 Visual ...............................................................................................................................14

- 4. Alternative Sites Considered..........................................................................................................15
- 5. Policy support for extension of time..............................................................................................19
- 6. Summary ........................................................................................................................................19

##### 1 Introduction

- 1.1 Purpose This report has been prepared to accompany a planning application which seeks permission to vary conditions 2 and 3 of PA 14/00689/C to extend the use of land at the former Ballakinnish Nurseries Site as a DOI Highways Depot for a further five years (to 13th January 2028), and in association with Town Centre Regeneration projects, Promenade Improvements, highway, drainage and flood alleviation construction projects. Along with the temporary storage of clinical sharps waste in 20ft shipping containers while the Secondary Waste Incinerator replacement is being built replaced, expected commissioning of the new plant planned for July 2026 and temporary storage of the clinical sharps waste until the end of 2026 to allow for any issues with the build, installation and commissioning of the new Secondary Waste Incinerator at the Energy from Waste site.

On 13th January 2015 planning permission 14/00689/C was granted for the ‘Change of use of site from a former market garden to use for the storage of construction materials (retrospective)’ these materials arising from the then current projects in Douglas, namely;

- • Town Centre Regeneration;
- • Promenade Improvements

The approval from DoI to replace the Secondary Waste Incinerator (SWI) has been submitted to SUEZ. It is expected the build and installation will be completed by mid-2026. The replacement of the current SWI is required due to extensive refractory damage which at any time could totally collapse and leave the Island without a facility to dispose of clinical waste from hospitals, GPs surgeries etc.

During build and installation phase sufficient clinical waste should be stored to ensure there is a sufficient quantity of clinical waste to commission the new SWI. Currently the SWI is only operated every 6 months, this has been done to prolong its operational life while treasury approval of £3,000,000 was obtained to purchase a replacement. During this time the bagged clinical waste has been incinerated in the Primary Waste Incinerator (PWI) and the clinical sharps waste stored in six to eight 20ft shipping containers stored at the Animal Waste Processing Plant (AWPP).

For the commissioning of the SWI, the quantity of clinical waste collected over 6 month is not sufficient, the commissioning of the new SWI will require at least twenty 20ft shipping containers filled with clinical sharps waste. There is not sufficient storage space at either the AWPP the Energy

from Waste (EfW) facility for twenty 20ft shipping containers. An alternative nearby storage site has been identified as Ballakinnish as this site is secure, located near to the Energy from Waste Facility, controlled by DoI and has CCTV. It is proposed that storage of the 20ft shipping containers will first be the AWPP, the EfW and the additional storage at Ballakinnish to be utilised for up to twenty 20ft shipping containers.

- Condition 2 of the PA required that “the land shall not be used other than for the storage of construction materials in association with the Town Centre Regeneration projects and the Promenade Improvements and for no other purpose including use as a waste transfer station”.
- Condition 3 of the PA required that the ‘use hereby permitted shall be for a limited period of 8 years from the date of this approval and thereafter the use hereby permitted shall be discontinued and the land restored to its former condition.’

A copy of the decision notice and the Inspector’s Report for PA 14/00689/C are included in Appendix

- 1.

This Planning Statement:

- • sets out the reasons why this site continues to be required as a depot servicing highways construction projects in the east of the Island.
- • sets out the reasons why the site is needed for the temporary storage of clinical sharps waste in 20ft shipping containers
- • includes and, where necessary, updates the information on the environmental impact of the site use
- • provides where available information on the use of the site over the past 8 years

- 1.2 Background and Existing Layout Ballakinnish is situated approximately 4 miles North West of Douglas within the parish of Braddan. The site is positioned approximately 550m west of Spring Valley roundabout on the A5 New Castletown Road, see drawing HW/2208/I1/050.

The A5 is designated as a primary distribution route providing direct access to Ronaldsway Airport as well as the south of the island. The route carries approximately 16,500 vehicles per day and along this section of the road, there is a 50 mph speed limit in operation.

In 1971 Ballakinnish started operating as a nursery, growing and selling cut flowers. Initially the business operated from 2000m2 of growing area under glass; gradual expansion over the following years took place such that in 1985, the growing area had increased to 15,500m2.

Picture1: Ballakinnish operating as a nursery

The site is mainly bounded by mature hedges and trees, with the A5 forming the southern boundary. Beyond the boundaries are agricultural fields. Amongst the fields are 4 properties, indentified in picture 2.

- • Ballakinnish House (derelict) • Ballakinnish
- • Croyton • Brookside

|Ballakinnish House|
|---|

### N

|Ballakinnish|
|---|

|Croyton|
|---|

|Brookside|
|---|

Picture 2: Ballakinnish Nursery Site (18 acres) sold to Isle of Man Government and surrounding properties.

Other notable features close to the site are as follows (identified in Picture 3):

![Aerial site plan showing the application site boundary outlined in red, with labels indicating nearby properties such as Ballakinnish House and Croyton.](https://images.planningportal.im/2023/01/7067367.png)

![A minimalist graphic showing a red outline of an irregular polygon on a black background, representing a site boundary.](https://images.planningportal.im/2023/01/7067368.png)

- • Private storage facility (180m south east)
- • Isle of Man Energy from Waste Facility (190m south)
- • Industrial Starter Units (270m south east)
- • Ballalough, Isle of Man Farmers (275m south west)

The previous occupier left the site in 2008 after selling it to the Isle of Man Government. In 2010 the then Department of Transport utilised the area as a site compound during construction of the Richmond Hill Highway Improvement scheme.

During this period, the site housed a welfare cabin along with construction materials and excavated arising’s required for the construction of the highway scheme.

Following completion of the Richmond Hill Highway scheme, the Department of Infrastructure continued to utilise Ballakinnish for storing construction based material. This has proved to be extremely beneficial to the operational requirements of the Department.

|Private|
|---|

|I.O.M. Energy from Waste Facility|
|---|

| |
|---|

|Starter Units|
|---|

Picture3: Area of Ballakinnish identified for material storage (3 acres) and surrounding notable features

In 2014 the DOI submitted a retrospective PA 14/00689 for change of use of 3 acres of land at the former nursery site is site, from market garden to material storage. The change was to allow the Department to store construction materials and excavated arising’s from two current projects in Douglas, namely;

![Aerial site location map showing a red-outlined plot of land in a rural setting with nearby facilities labeled.](https://images.planningportal.im/2023/01/7067369.png)

- • Town Centre Regeneration;
- • Promenade Improvements.

Since 2014, the Department of Infrastructure has not received any adverse comments regarding the site and are unaware of any complaints regarding their operations at Ballakinnish.

The site has continued to operate as envisaged to support the stock of materials for the regeneration and promenade schemes. Since completion of these schemes it continues to be operated for other local sites including the Richmond Hill drainage improvements and the current Victoria Street works. Daily volumes of traffic have been reduced since the completion of the Promenade scheme and it is envisaged these will remain at a lower level than detailed in the original application.

- 1.3 Justification for the Continued Use of the Site The Department of Infrastructure is continually striving to improve operational efficiencies to the benefit of the Island, and to minimise the environmental impact of its operations, specifically in relations to consumption/combustion of fossil fuel in its operational fleet, plant and equipment. This is in accordance with the targets for reducing greenhouse gas emissions contained within the Climate Change Act 2021 and associated Climate Plan 2022, and replicated in the Government’s Our Island Plan. The Department has considerable future plans for continued works and improvements within Douglas and the east of the Island. It is imperative therefore that it is able to maintain a supply of materials and a storage depot in this eastern area of the Island.

Over the next 5+ years the Department has plans for further refurbishment of Douglas Promenade which will include;

- • Refurbishment of the walkway;
- • Construction of raised sea defence walls to protect the walkway and promenade;
- • Replacement of railings;
- • Coastal protection rock armour
- • Continuation of the tram track from Broadway to Sea Terminal (Tynwald commitment)

Additionally the following highway and flood alleviation schemes are planned in the eastern area which will benefit from access to the Ballakinnish site for storage of materials;

- • Douglas Flood Alleviation

- • Victoria Road Crossing
- • Parade Street Crossing
- • Fort North Roundabout to Richmond Hill resurfacing
- • Bus Stop Kerb Replacement Programme
- • Footway and PERS Programme
- • A5 Santon to Ballalonna
- • High Street, Port St Mary
- • Ridgeway Street, Douglas

Highways currently utilises the materials storage compound at Ballakinnish to supply all of its eastern construction sites. The number of vehicle movements into the main streets of Douglas and the surrounding areas are managed in an efficient manner from the Department’s depot rather than a wholesale supplier thus minimising the deliveries to the Island and reducing the number of deliveries required by the local suppliers to a town centre site. The environmental benefits of reducing construction traffic are a reduction in congestion, noise, pollution and carbon emissions. Return journeys from site can be used for waste removal. These processes also meet the Departments goals of introducing “just in time” delivery and lean management and following best practice outlined in the WRAP document “Using Construction Consolidation Centres to Reduce Construction Waste and Carbon Emissions”. Additionally, there is an added visual and societal benefit of minimising the quatinty of materials stored on town centre sites by maintaining smaller, cleaner sites and less fencing to obstruct public views.

The central location of the Ballakinnish site works particularly well for all projects on the east, central and southern parts of the Island, and is the only location where there is ample area to store the large stockpiles of paving, pipes, fittings etc. with easy access to the highway network for deliveries to and from the site. None of the Department’s other highways depots are of sufficient size to meet these needs. The Department has lost the facility to store materials at its main Ellerslie Depot as this land is now rented out to the private sector by the landowner.

- 1.4 Justification for use as temporary storage for clinical sharps waste The Department of Infrastructure has placed an order through SUEZ for a new SWI which will replace the current SWI, which is beyond repair. While the new SWI is being build and commissioned there is a requirement to obtain sufficient clinical waste for the commissioning of the plant. It is expected that the commissioning will require 40-90 tonnes of clinical waste. This volume of waste generated over 18 months at the hospital. To store this amount of waste would require approximately twenty 20 ft shipping containers. The 20ft shipping containers will have to be stored in a secure location

close to the Energy from Waste facility to ease moving the waste to the Energy from Waste when required during the commissioning phase of the new SWI.

The location of the Ballakinnish site works particularly well for the temporary storage of the 20ft shipping containers, being across the road from the Energy from Waste facility. The site is secure with a lockable gate, and CCTV. The site had sufficient hardstanding for the 20ft shipping containers.

##### 2. Proposal

- 2.1 Duration & Hours of Normal DoI Operation There are no changes proposed to the hours of operation.

The hours of operation will reflect the current operating hours of the Departments working arrangements:

- • 07.30 – 18.00 Monday to Friday and
- • 08.00 – 14.00 Saturday.

- 2.2 Duration & Hours of Clinical Sharps Waste Operation The hours of operation will reflect the current transport of clinical waste from the hospital to the Energy from Waste facility with two or three deliveries a week of the clinical waste being transferred to Ballakinnish during the hours:

- • 07.30 – 18.00 Monday to Friday and
- • 08.00 – 14.00 Saturday.

During commissioning access to the clinical waste maybe required outside these hours especially at weekends and later in the day when the plant is operational 24/7. Out of hours access to the site where possible will be kept to a minimum.

- 2.3 Site Security The site currently benefits from natural boundary features which facilitate a good level of security. The planned installation of heras fencing was not progressed. On review it was considered that the site is secure, the materials are not easily removed, and the security offered by the existing gated entrance and CCTV was sufficient. The 20ft shipping containers containing the clinical waste sharps will be locked.

Vehicular and pedestrian access to Ballakinnish will continue from the A5 New Castletown Road. A safe area is provided for articulated vehicles off the highway before the locked gate requires access.

It is anticipated the gate will be locked at all times outside of the operating hours specified above. During operating times the site will be left vacant; security will be provided with CCTV cameras

- 2.4 Material Storage Ballakinnish will be used to store materials for various highway, drainage and flood alleviation construction projects. Material types stored include:

- • Natural Stone Paving (Granite) • Street Lighting Columns • Road Gullies
- • Composite Stone Paving (Kellen) • Tegula Paving Units • Concrete Kerbs
- • Concrete / Clay Paving Units • Jointing Mortar • UPVC Ducts
- • Granite Kerbs & Channels • Manhole Rings • Drainage products
- • Type 1 Granular Material • Inspection Chambers • Excavated Arising’s

Excavated arisings are only temporarily stored at Ballakinnish. The volume of material on site at any one time is kept to a minimum and is removed to a recycling depot or to tip on a monthly basis, or

- as and when the stockpile becomes sufficiently large to make removal economically viable.

- 2.5 Clinical Sharps Waste Storage The 20ft shipping containers containing clinical waste will only be temporarily stored at Ballakinnish. The volume of 20ft shipping containers on site at any one time is kept to a minimum and will be removed once commissioning of the new SWI is completed.

The 20ft shipping containers will not be stacked, placed on hardstanding surface, and has the dimension as shown in Picture 4.

Picture4: 20ft shipping container dimensions

![drawing from page 10](https://images.planningportal.im/2023/01/7067370.jpg)

- 2.6 Vehicle Movements When Ballakinnish was used as a nursery the approximate weekly vehicle usage was

• 70 motor cars • 14 light goods vehicles • 3 articulated vehicles The proposed weekly vehicle usage for the material storage facility will average; • 50 light goods vehicles • 3 tipper lorries • 1 articulated vehicle The proposed weekly vehicle usage for the clinical sharps waste storage facility will average; • 1- 2 light goods vehicles

It is intended the LGV’s (2, 3 and 4 axle) visiting on a daily basis will be attending the facility during the operational hours stated in 2.1 above.

It is anticipated the four axle tipper lorries visiting site will do so fortnightly on one day (6 No.) between the hours of 8.30 and 3.30, Monday to Friday.

Articulated vehicles will bulk deliver materials approximately every 10 weeks. Deliveries will usually be carried out over two days, with multiple articulated vehicle trips between the hours of 09.00 and 17.00 Monday to Friday.

Drivers approaching the access are able to see the entry from a distance of at least 160m (the minimum distance stated in the Design Manual for Roads and Bridges) from the A5.

The new site entrance proposed in PA 14/00689/C was not developed. On review it was considered that the existing site access provided adequate sight lines for vehicles entering and exiting the site.

##### 3. Environmental Impact

- 3.1 General Site storage is limited on regeneration and promenade schemes. Bulk storage of materials at these sites will have a negative impact on amenity. The daily movement of plant and machinery required to access the stored materials will pose a safety issue to the public and other vehicle users. To minimise any impacts the Department are proposing to bulk store materials at Ballakinnish, away from the working areas. Ballakinnish is ideally located to allow full utilisation of resource and not impact on the programmed delivery of the schemes.

Predominately the materials to be stored will be inert natural stone, concrete and clay paving units. Materials required for activities such as drainage and ducting works, relaying tram tracks and fencing will also be stored at Ballakinnish.

Materials will be delivered to Ballakinnish on articulated lorries from either Douglas or Ramsey harbour. Once on site, the material will be unloaded using a site master excavator and placed into designated areas according to project requirements.

Any excavated arising’s stored at Ballakinnish will be brought to site on 2, 3 or 4 axle lorries depending upon the volume of material involved. All imported material will be free from any contaminants.

Collection of materials for the construction schemes will be done on a daily basis using a lorry. When there is a suitable quantity of excavated arising’s, these will be removed for recycling or to tip, using

- 4 axle tipper lorries, thus minimising the number of trips required.

- 3.2 General Clinical Sharps Waste The clinical waste will be transfer to the Ballakinnish site in Dolav boxes, these will be emptied inside a 20ft container and the UN approved clinical waste will be stacked to maximise the storage space within the 20ft shipping container. The UU approved containers will stacked and supported to ensure then do not fall. Small UN approved containers that are difficult to stack will be placed in builders bags.

The 20ft shipping container will remain static and will not be moved while there is clinical waste within the 20ft shipping container. The removal of the clinical waste and stacking of the clinical waste containers will be carried out following the requirements and controls within a Risk Assessment and Safe Working Procedure. After each removal of the clinical waste from the Dolav containers and appropriately stacked, the 20ft shipping container will be locked.

If a disturbance of the 20ft shipping container is noticed then the CCTV will be reviewed to assess the source of the disturbance and the police informed if the disturbance was from unauthorised access.

- 3.3 Noise As a material storage facility, up to 55 vehicles (all lorries of various sizes) will visit the site every week. There will also be a site master excavator permanently on site, for the purpose of loading / unloading materials from the delivery vehicles.

The vehicular activity will create noise. However modelling indicates that this will not be at a level to cause a nuisance to the occupants of properties adjacent to the site: Ballakinnish; Croyton, and Brookside. Using formula and charts issued by the Department of Transport UK, two simple noise calculations have been carried out.

- • For traffic operating on A5 New Castletown Road, this calculation will give an indication of the traffic noise already experienced at the properties, the second calculation is
- • For traffic within the proposed site at Ballakinnish.

A third calculation combines the two noise figures and determines the overall increase (if any) in noise resulting from the material storage facility. The results are summarised in the table below.

|Property<br><br>|Noise Level [L10(18hour) dB(A)]|Noise Level [L10(18hour) dB(A)]|Noise Level [L10(18hour) dB(A)]|
|---|---|---|---|
|Property<br><br>|Road|Site|Combined|
|Ballakinnish|61.6|48.4|61.8|
|Croyton|65.6|41.5|65.6|
|Brookside|58.3|38.0|58.3|

Table 1: Basic noises calculations

The table clearly shows the proposed material storage facility will have no noise impact on Croyton and Brookside and only a negligible impact on Ballakinnish. However these figures are for general road traffic and do not take into account any special devices such as reversing beepers.

To mitigate any noise pollution caused by reversing vehicles;

- • The site will be separated into specific storage areas, vehicles accessing the area to deposit / collect materials will do so in a forward direction.
- • The site layout will also be such that vehicles leaving a storage area will do so in a forward direction only.
- • Any storage area where reversing is unavoidable (i.e. excavated arising’s and type 1) will be located furthest away from the houses. This will be in the north east corner of the site.

In the past 8 years there have been no complaints about noise nuisance from use of the site.

- 3.4 Vibration A construction site has the potential to cause nuisance and physical damage through vibration. Research has shown that vibration nuisance is closely linked to noise nuisance. The material storage

- facility has no demonstrable effect on noise. In the past 8 years there have been no complaints about vibration nuisance from use of the site.
- 3.5 Water / Soil Pollution All materials to be stored at Ballakinnish are inert. There is no risk of water or soil pollution from any of the materials. In the past 8 years there have been no complaints about water course or soil pollution. The DEFA Environmental Protection Unit has carried out a pre WDL site consultation. No concerns were raised. All clinical waste will be stored in UN approved containers and stacked within the 20ft shipping containers will no movement of the 20ft shipping containers. Any spillage will be retained and cleared up inside the 20ft shipping container. Therefore there is negligible pollution risk to water courses or soil.
- 3.6 Dust / Air Pollution Ballakinnish as a material storage facility will have a negligible impact on dust / air pollution due to the types of materials stored there. Most materials to be stored (see section 2.3) do not generate any dust / air pollution. However, the storing of excavated arising’s and Type 1 granular material will present a minor dust nuisance.

Dust is only likely to affect the property Ballakinnish. As with noise, to mitigate any impact from dust their storage will be furthest away from the house, in the north east corner of the site.

Generation of dust through vehicle movements particularly on unpaved roads can account for a significant proportion of dust nuisance which can be exacerbated in dry or windy conditions. To reduce dust created by vehicles, suitable dust suppression activities are carried out during periods of dry weather.

A number of methods to minimise dust caused by moving vehicles were initially considered by the Department, for example paving haul routes and installing a wheel wash. They were not proposed due to the low levels of dust likely to be created and the costs involved in installing them. In the past 8 years there have been no complaints about dust pollution. The DEFA Environmental Protection Unit visited the site to assess the need for a waste disposal licence and raised no concerns about the environmental impact of site operation.

Ballakinnish as a temporary clinical waste material storage facility will have a negligible impact on dust / air pollution due to the types of materials stored there. All the clinical waste will be in UN approved containers stacked inside 20ft shipping containers.

Generation of dust through vehicle movements particularly on unpaved roads can account for a significant proportion of dust nuisance which can be exacerbated in dry or windy conditions. Due to the low level of vehicle movement and the 20ft shipping containers will be on a hardstanding area there will be negligible impact on dust / air pollution due to vehicle movement.

- 3.7 Ecology Ballakinnish is surrounded by farm fields. The boundary between the fields and the site is a combination of mature trees and sod hedges.

Until 2007 the site operated as a Nursery, after which the nursery relocated and the site became derelict, leaving the site vacant with only limited evidence available of its previous use.

In 2010 the Department of Transport took possession of the site for use as a compound for the highway improvement scheme on Richmond Hill. To create the compound, excavated arising’s and soil were imported to build up the areas in between the concrete strips to make the site more usable.

The levelling of the site has been carried out without having any impact on the site boundaries or the surrounding fields. A rapid ecological survey on part of Ballakinnish site was undertaken in August 2021 (Appendix 2 MWT ‘Ecological Advice: Ballakinnish Nurseries, Braddan, Isle of Man’) This concluded that, while ‘it is a brownfield site, it contains valuable wildlife habitat for invertebrates and breeding birds and may be used by Common Lizard and Common Frog as terrestrial habitat.’ ‘As much of the site as possible should be preserved for its value to wildlife. In particular, field margins, hedgerows and scrub should be retained.’ This study did not identify any detrimental impacts of the current site use on the ecology of the site.

- 3.8 Visual Ballakinnish is situated on the eastern slopes of a valley. The site is surrounded by fields and trees on three sides and the A5 primary distributor on the fourth. Further afield is the Energy from Waste Facility. Both sites are clearly visible from the A5 Richmond Hill on the western slopes of the valley.

|Energy from Waste Facility|
|---|

|Ballakinnish|
|---|

Picture5: View of site and surrounding area from Richmond Hill

When the site operated as nursery it was visible from the A5 Richmond Hill, even more so during periods of dusk / darkness when it operated under floodlights (picture 7). The makeup and operation of the site as a storage facility means it is also easily identified from Richmond Hill.

As the proposal is temporary storage of clinical waste within single stacked 20ft shipping containers the visual impact is temporary and low.

Although The Department proposed initially to plant approximately 44 standard size trees along the western boundary of the site, this was not undertaken. The vegetation on the site was found to be both well established and enhancing local biodiversity. The colours of the materials stored are natural greys browns and greens, and the height of stored materials is low. Although visible from Richmond Hill the site it not formally developed ie built on. In the past 8 years there have been no complaints about the visual impact of the site or its operation.

- 4. Alternative Sites Considered The Department has reviewed the list of alternative sites considered, and dismissed, for PA 14/00689/C. These alternative locations either continue to be deemed unsuitable, due to the area available or the proximity / distance to the construction sites, or are no longer available (see below). No new alternative sites have been identified.

![map or plan from page 16](https://images.planningportal.im/2023/01/7067371.png)

The Department has lost access to land at Ellerslie Depot that it previously leased resulting in the loss of approximately 6,800m2 of valuable material and equipment storage space. Following the loss of parking area at Ellerslie, as well as the loss of registration for vehicles to be parked overnight at the former Vehicle Testing Centre in Braddan, Ballakinnish has been registered as an “O” Licence Operating Centre for parking of 12 Department vehicles associated with the construction works in the Eastern area. Currently up to 4 vehicles are parked on the site overnight.

Policy for provision of Depots for Highways The Department acknowledges the need for a strategy for provision of depots around the island. This includes permanent depots, as well as temporary depots to service area specific projects. The DoI produced its depot strategy in 2010 which identified the need for new regional depots but due to financial constraints has not progressed. It is envisaged that, when economic circumstances allow, this strategy will be revisited by the DOI with a view to identifying both permanent and possible temporary locations. This may involve joint or shared site uses.

In the short term the Ballakinnish site is needed for ongoing Departmental projects. In the event that planning permission is not granted for an extension of time, the Department is unlikely to be able to progress these projects due to increased cost and delay. The materials will need to be stored

- at a number of locations across the island as there are no Depots with capacity to accommodate all materials. Materials will have to be hauled in loads that are not economic. This will increase the number of vehicle movements, total miles travelled, and associated GHG emissions.

The Department has reviewed alternative sites for the temporary storage of clinical sharps waste in 20ft shipping containers and considered them unsuitable, due to:

- • Location, distance from the Energy from Waste Facility
- • Lack of security
- • Lack of space
- • Excessive cost of storage

#### Alternative sites

###### Douglas Promenade Walkway

Logistically the walkway would be the preferred site as it is close to the working areas, minimizing haulage and travel time. However, given the large volumes of material to be stored and the general

public use of the area this is not considered to be a practical solution or acceptable on day to day safety grounds or visually given the tourist and recreational facility provided by the walkway. In addition, use of the promenade walkway would not be allowed during events such as TT, the Parish Walk, IOM triathlon, Manx Grand Prix, Junior Cycling Races & Manx Rally etc.

| |
|---|

Picture6: View of site and surrounding area from Richmond Hill

###### Summerland Site

This site is owned by the Department of Infrastructure and is currently up for sale. Private developers have expressed an interest in developing the site; subsequently the saleability of the site would be greatly reduced if an area of it was being used as a storage compound. Manx Development Corporation are looking at development options and have recently carried out site investigation works in preparation for design development.

Nobles Hospital Site This site has developed and is no longer available, and does not have the sufficient space for the quantity of 20ft shipping containers required and the site is not secure.

###### Jurby Industrial Estate

A further option for consideration is the Departments facilities at Jurby. Although near to Ramsey Harbour, it is too far away from Douglas (3 – 4 hour round trip) for it to be financially and environmentally viable for materials to be collected / deposited on a daily basis.

![A photograph of a rural site featuring a large agricultural building, a paved area with parked cars, and wooden fencing.](https://images.planningportal.im/2023/01/7067372.jpg)

Fish Yards, Peel The DEFA owned fish yards in Peel is another location for consideration. As with Jurby the travelling distances and resulting inefficiencies rule this site out.

Old Meat Processing Plant, Tromode. This site has been developed and is no longer available.

Existing Depots Ellerslie Depot This site is no longer available.

Ballasalla The Department’s Ballasalla depot could be made available for material storage. Similar to Jurby this is a particularly poor choice of site due to the long haulage distance for initial material storage and collection for daily supplies to the sites. An average return journey time including loading and unloading would be in the region of 3-4 hours and would lead to working inefficiencies.

Hillberry A further Department depot is at Hillberry which again could be made available. However, access to this site is from the TT course. Visibility at the entrance is poor and the Department is trying to minimise the use of this depot for these reasons.

Privately Owned Sites Situated around Douglas are a number of privately owned industrial estates such as

- • White Hoe Industrial Estate, Castletown Road • Middle River Industrial Estate, Pulrose Road
- • Snugborough Industrial Estate, Peel Road • Kirby Farm Industrial Estate, Vicarage Road

All of these sites have suitable areas for the Department to use as a material storage facility. However they all charge a premium cost for usage and would not provide Government with value for money. As such no privately owned sites have been considered further.

Middle Park Recycling While middle Park Recycling facility is next to the Energy from Waste facility, Planning permission as a Waste Operations site with a Waste Disposal Licence it is privately owned. The financial cost for the temporary storage of clinical sharps waste would be in excess of £100,000 and require treasury approval for the funding during a time where the government is looking for efficiency

savings. Access to the site may be restricted to operational times that are not convenient during the commissioning phase.

##### 5. Policy support for extension of timeStrategic Plan Policies

The site is not allocated as a highways depot within the Area Plan for the East. It is within an area of high landscape value. General Policy 3 states that development will not be permitted outside of areas zoned for development. However there are exemptions. It is considered that proposed continued use of Ballakinnish site meets Policy GP3 (e) in that it is location-dependent development in connection with the provision of necessary services; and Policy GP3 (g) in that the development is of overriding national need in land use planning terms, and there is no reasonable and acceptable alternative. Spatial Policy 1 identifies that Douglas urban area ‘will remain the main employment and services centre for the Island.’ The Department is required to develop and maintain the infrastructure necessary support this location dependent Policy.

Our Island Plan incorporating the delivery of the economic strategy

In delivering ‘An Environment we can be proud of’ the Island Plan aims to

- • Ensure a vibrant Island offer for young people today and attract people to live and work on the Island to grow the economically active population.
- • Ensure street policy is informed by communities so that streets and places are inclusive, easy to navigate, safe and healthy and reflect the wishes of the people who live there.
- • Develop a Plan for Climate Change Adaptation, including flood management and mitigation.
- • Deliver the Climate Change Action Plan (which is based on the Professor Curran Action Plan), to achieve our Climate Change goals.

The Department projects serviced by the Ballakinnish Depot support these aims.

###### 6. SummaryThis report has been prepared to accompany a planning application which seeks permission to varycondition 2 and 3 of PA 14/00689/C to extend the use of land at the former Ballakinnish NurseriesSite as a DOI Highways Depot for a further five years (to 13th January 2028) and in association withTown Centre Regeneration projects, Promenade Improvements, highway, drainage and floodalleviation construction projects.

- Condition 2 of the PA required that “the land shall not be used other than for the storage of construction materials in association with the Town Centre Regeneration projects and the Promenade Improvements and for no other purpose including use as a waste transfer station”.

- Condition 3 of the PA required that the ‘use hereby permitted shall be for a limited period of 8 years from the date of this approval and thereafter the use hereby permitted shall be discontinued and the land restored to its former condition.’

A copy of the decision notice for PA 14/00689/C is included in Appendix 1

The site has been operating over the past 8 years without complaint. There is a demonstrable and on-going need for the site to meet the operational requirements of the Department in the east of the Island. There are no alternative suitable non-commercial sites available for materials storage. A number were considered by rejected as being too;

- • Far away from Douglas, therefore increasing vehicle emissions and operating costs;
- • Expensive to set up, reducing monies available for the construction schemes;
- • Disruptive to the general public. On going use of Ballakinnish will reduce vehicle emissions, road hazard and impact on the national road infrastructure, and reduce costs to the taxpayer. Site operations will continue as at present.

Environmentally the facility will not significantly impact on the local surroundings.

It is acknowledged that the Department would benefit from a strategy for provision of operational depots both permanent and project specific. There is a need, as part of this strategy, to identify a suitable Depot in the east to service the infrastructure requirements of the capital and periphery. However, this is medium term objective and is subject to resources and funding availability. When Ballakinnish is no longer required it will be cleared of material and hardstanding, vacated and suitably landscaped.

Ballakinnish best meets the need for a material storage facility to support the Departments needs for the east and ongoing development works to Douglas Promenade. It has access onto the primary distributor network, is located away from residential areas, its proximity to Douglas Town Centre and minimal establishing cost provides significant financial and environmental benefits to all other considered locations.

Ballakinnish best meets the need for the temporary storage facility of clinical sharps waste to support the Departments needs while the new Secondary Waste Incinerator is being built and commissioned. It has access onto the primary distributor network, is located away from residential areas, and

###### location is next to the Energy from Waste facility. It requires minimal establishing cost provide significant financial and environmental benefits to all other considered locations.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/55575-braddan-ballakinnish-nurseries-ballakinnish/documents/1100568*
