**Document:** DEC Decision Notice
**Application:** 14/00644/C — Additional use of self-contained apartment as tourist accommodation
**Decision:** Permitted
**Decision Date:** 2014-07-11
**Parish:** Lonan
**Document Type:** decision / decision_notice
**Source:** https://planningportal.im/a/34755-lonan-oirr-ushtey/documents/1089623

---

# DEC Decision Notice

Juan Andreays Kinnish
Oirr-Ushtey
The Promenade
Laxey
Isle Of Man
IM4 7DD

## Town and Country Planning Act 1999

### The Town and Country Planning (Development Procedure) (No 2) Order 2013

In pursuance of powers granted under the above Act and Order the Department of Infrastructure determined to **APPROVE** a planning application by Juan Andreays Kinnish, Ref **14/00644/C**, for the additional use of self-contained apartment as tourist accommodation at Oirr-Ushtey The Promenade Laxey Isle Of Man IM4 7DD subject to compliance with the following condition(s):

1. The development hereby approved shall be begun before the expiration of four years from the date of this decision notice.

**Reason:** To comply with article 14 of the Town and Country Planning (Development Procedure) (No2) Order 2013 and to avoid the accumulation of unimplemented planning approvals.

This approval relates to Drawings reference JK1, JK2A, JK2B and 3 all received on 23rd May 2014.

**Date of Issue:**
11th July 2014

M Gallagher

### Director of Planning and Building Control

**Guidance Note** This decision was made by the Head of Development Management in accordance with the authority delegated to her. This permission refers only to that required under the Town and Country Planning (Development Procedure) (No 2) Order 2013. Any appeal against this decision must be in accordance with Article 8 of the Order.

A valid appeal must be in writing, signed by the appellant, and submitted to the Department within 21 days of the date of this Notice. To further validate the appeal it must contain:

- Payment of a planning appeal fee as prescribed in an order made by the Department under Section 1(1) of the Fees and Duties Act 1989 (currently £150);
- The reasons for making the appeal; and
- An election to have the appeal conducted by means of an inquiry (a hearing) or by means of written representation.

An appeal form and guidance notes are available from either Planning & Building Control, Tel 685950, or to download from the Department's website http://www.gov.im/categories/planning-and-building-control/planning-development-control/planning-appeals/how-to-appeal/

Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, are available for inspection at the Department.

The proposed development must not be commenced until either;

- The time for requesting an appeal has expired; or
- Any appeal has been determined;

Whichever is the later.

If no appeal is lodged within 21 days of the date of issue overleaf, and this decision becomes final, the Department's public reference copy (counter copy) of the planning application may be collected by the applicant or their agent from Murray House.

Please note that if the counter copy of the application is not collected within THIRTY DAYS following the last date on which a planning appeal can be made it will be destroyed without further notice.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/34755-lonan-oirr-ushtey/documents/1089623*