# Officer Report

**Application No.:** 25/00491/LAW
**Applicant:** Ms Kathryn Ford
**Proposal:** Certificate of Lawful Development for installation of roof light
**Site Address:** 11 Slieau Whallian Park St Johns Isle Of Man IM4 3JH
**Planning Officer:** Peiran Shen
**Expected Decision Level:** Officer Delegation
**Recommended Decision:** Certificate of Lawful Use/Devel Approved
**Date of Recommendation:** 09.06.2025 _________________________________________________________________

## Conditions and Notes for Approval

C : Conditions for approval N : Notes attached to conditions

C 1. There is sufficient evidence demonstrating that the rooflight has been in situ since 2010. Plans/Drawings/Information;

This decision relates to the documents, location plan, site plan, Google StreetView photo and existing photo, which have all been received on 15th May 2025.

_________________________________________________________________ Officer’s Report

1.0 INTRODUCTION - 1.1 The application seeks a Certificate of Lawful Development in respect of the installation of a rooflight. The application seeking the Certificate of Lawfulness was submitted on 15th May

2025. It means the relevant 4 years for consideration are from 15th May 2021.

1.2 In accordance with the provisions of Schedule 4, Part 1, paragraph 3 of the Town and Country Planning Act 1999 ("the Act"), a development carried out in breach of planning control shall become immune from enforcement action after a certain period of time, provided that formal enforcement action has not already been taken. The relevant time periods are set out below:

- a) in respect of a breach of planning control consisting of the carrying out without planning approval of the building, engineering, mining or other operations in, on, over or under land, after the end of the period of 4 years beginning with the date on which the operations were substantially completed;
- b) in respect of a breach of planning control consisting of the change of use of any building to use as a single dwelling house, after the end of the period of 4 years beginning with the date of the breach;
- c) in respect of any other breach of planning control, after the end of the period of 10 years beginning with the date of the breach.

1.3 Section 24 of the Act makes provision for the submission and issuing of a Certificate of Lawfulness to establish the lawfulness of a breach of planning control. - 1.4 An application for a Certificate of Lawfulness is determined based on fact. Unlike an application for planning approval, it is not concerned with land-use planning considerations or the impacts of the development upon the public realm. - 1.5 The principal test is whether, on the balance of probabilities, the breach of planning control occurred in excess of four years ago. If the Planning Authority has no evidence of its own to contradict that provided by the applicant, then provided if the applicant's evidence is sufficiently precise and unambiguous, a Certificate of Lawfulness may be issued. It is not usually necessary for the Planning Authority to corroborate the applicant's evidence.

2.0 THE SITE - 2.1 The application site is 11 Slieau Whallian Park, St Johns.

3.0 THE PROPOSAL - 3.1 The application seeks a Certificate of Lawful Development for the installation of a rooflight.

4.0 PLANNING HISTORY - 4.1 There is no previous application considered materially relevant to this application.

5.0 REPRESENTATION - 5.1 German Parish Commissioner has not commented at the time of this report (09.06.2025).

6.0 ASSESSMENT / SUMMARY OF EVIDENCE PROVIDED - 6.1 In terms of whether the installation of a rooflight has taken place for more than 4 years from the date of submission, the Department considers that they have. The most relevant evidence is the Google StreetView Images taken in 2010. Within these, it is clear that the installation of a rooflight was completed by 2010. Hence, the installation of a rooflight took place longer than the required 4-year period.

7.0 CONCLUSION - 7.1 On the balance of probabilities, the evidence demonstrates that the rooflight was in situ for more than 4 years. As such, the Department may not issue an enforcement notice due to the provisions of the Town and Country Planning Act 1999 Schedule 4 Part 1 paragraph 3(a), and it is recommended that a Certificate of Lawful Development is granted.

8.0 RECOMMENDATION - 8.1 It is recommended that the application for a Certificate of Lawfulness is agreed.

9.0 INTERESTED PARTY STATUS - 9.1 As the application is for a CLD, it is not required to be assessed. _____________________________________________________________________________________________________

I can confirm that this decision has been made by a Principal Planner in accordance with the authority afforded to that Officer by the appropriate DEFA Delegation and that in making this decision the Officer has agreed the recommendation in relation to who should be afforded interested person status and/or rights to appeal.

Decision Made : Certificate of Lawful Use/Devel Approved Date: 10.06.2025 Determining Officer

Signed : J SINGLETON Jason Singleton Principal Planner

Customer note This copy of the officer report reflects the content of the office copy and has been produced in this form for the benefit of our online service/ customers and archive record.

---

*Data sourced from the Isle of Man public planning register under the [Isle of Man Open Government Licence](https://www.gov.im/about-this-site/open-government-licence/).*
*Canonical page: https://planningportal.im/a/34168-st-johns-11-slieau-installation-roof/documents/1087022*